Resources Legislation (Fee Unit Conversion) Amendment Regulation 2022


Queensland Crest

Part 1 Preliminary

1Short title

This regulation may be cited as the Resources Legislation (Fee Unit Conversion) Amendment Regulation 2022.

2Regulation amended

This part amends the Acquisition of Land Regulation 2014.

3Amendment of s 3 (Fee—Act, s 9)

(1)Section 3(a), ‘$203.70’—
omit, insert

203.70 fee units

(2)Section 3(b), ‘$203.70 plus $60.45’—
omit, insert

203.70 fee units plus 60.45 fee units

Part 3 Amendment of Fossicking Regulation 2019

4Regulation amended

This part amends the Fossicking Regulation 2019.

5Replacement of sch 6 (Fees)

Schedule 6
omit, insert

Schedule 6 Fees

section 36

Fee units

1

Individual fossickers licence—

(a)  for 1 month

8.80

(b)  for 6 months

33.40

(c)  for 1 year

56.25

2

Family fossickers licence—

(a)  for 1 month

12.60

(b)  for 6 months

42.85

(c)  for 1 year

75.15

3

Club fossickers licence

94.15

4

Educational organisation fossickers licence—

(a)  for 1 month

37.30

(b)  for 1 year

75.15

5

Commercial tour operator fossickers licence—

(a)  for 1 month

65.85

(b)  for 1 year

567.00

6

Individual fossickers camping permit or family fossickers camping permit—

(a)  for each whole week

26.50

(b)  for each additional night

4.20

7

Club fossickers camping permit or educational organisation fossickers camping permit, for each person who is to camp under the permit—

(a)  for each whole week

12.85

(b)  for each additional night

2.19

8

Commercial tour operator fossickers camping permit, for each person who is to camp under the permit—

(a)  for each whole week

26.50

(b)  for each additional night

4.20

9

Application for agistment approval, for each head of stock to be agisted (s 22(2)(c)(ii))

17.75

10

Agistment fee for an agistment approval (s 25(2)(a)), for each tag given, for each week of the period stated in the approval

0.42

11

Replacement fee for an agistment tag (s 27(2)(c))

17.75

6Regulation amended

This part amends the Geothermal Energy Regulation 2012.

7Amendment of s 80 (Security for geothermal tenure—Act, s 204)

Section 80(2)—
omit, insert—
(2)For section 204(2)(b) of the Act, the following amounts are prescribed—
(a)for a geothermal permit or proposed geothermal permit—14,748 fee units;
(b)for a geothermal lease or proposed geothermal lease—43,017 fee units.

8Replacement of schs 2 and 4

Schedules 2 and 4
omit, insert

Schedule 2 Annual rent

section 79(1)

  

Fee units

1

Annual rent for geothermal permit (Act, s 130(1))—for each sub-block included in the area of the permit

3.00

2

Annual rent for geothermal lease (Act, s 130(1))—for each square kilometre included in the area of the lease

162.00

Schedule 4 Fees

section 83

  

Fee units

1

Application for geothermal permit (Act, s 36(e))

1,356.00

2

Application for declaration of all or part of the area of a geothermal permit as a potential geothermal commercial area for the permit (Act, s 65(2)(b))

1,081.00

3

Application for geothermal lease over all or part of the area of a geothermal permit (Act, s 78(f))

1,356.00

4

Application for approval to amend development plan for a geothermal lease (Act, s 100(2)(b))

544.00

5

Fee for request for required information for a geothermal tenure (Act, s 196(1)(b))—

 
 

(a)  for information made available in electronic form, other than on a tape or cartridge

168.90

 

(b)  for information made available on a tape or cartridge

338.20

6

Application for renewal of a geothermal tenure (Act, s 292(c)(i))

676.00

9Regulation amended

This part amends the Greenhouse Gas Storage Regulation 2021.

10Amendment of s 33 (Security for GHG authorities)

Section 33(2)—
omit, insert—
(2)For section 271(2)(b) of the Act, the following amounts are prescribed—
(a)for a GHG permit or proposed GHG permit—16,350 fee units;
(b)for a GHG lease or proposed GHG lease—47,690 fee units;
(c)for a GHG data acquisition authority or proposed GHG data acquisition authority—14,305 fee units.

11Replacement of schs 1 and 2

Schedules 1 and 2
omit, insert

Schedule 1 Annual rent

section 30(1)

Fee units

1

Annual rent for GHG permit (Act, s 86(1))—for each sub-block included in the area of the permit

2.95

2

Annual rent for GHG lease (Act, s 168(1))—for each square kilometre or part of a square kilometre of the area for the lease

162.00

3

Annual rent for GHG data acquisition authority (Act, s 243(1))—for each sub-block included in the area of the authority

2.95

Schedule 2 Fees

section 35

Part 1 GHG authority fees

Fee units

1

Tender for GHG permit (Act, s 35(d))

1,456.00

2

Application for approval to amend the work program for a GHG permit (Act, s 68(b))

584.00

3

Giving proposed later work program for a GHG permit to the Minister within the time required under section 91(3) of the Act (Act, s 91(6), definition relevant fee, paragraph (a))

584.00

4

Application for renewal of GHG permit (Act, s 94(1)(d)(i))

726.00

5

Application for a declaration that all or a stated part of the area of a GHG permit is a potential storage area for the permit (Act, s 101(2)(b))

1,164.00

6

Permit-related application for a GHG lease (Act, s 114(d))

1,456.00

7

Application for approval to amend the development plan for a GHG lease (Act, s 157(2)(b))

584.00

8

Giving proposed later development plan for GHG lease to the Minister within the time required under section 172(3) of the Act (Act, s 172(6), definition relevant fee, paragraph (a))

584.00

9

Surrender application for a GHG lease (Act, s 177(1)(b))

584.00

10

Application for approval of proposed GHG coordination arrangement (Act, s 188(2)(b)(ii))

584.00

11

Application for GHG data acquisition authority (Act, s 234(b))

438.40

Part 2 General GHG authority fees payable under chapter 5 of the Act

Fee units

1

Fee for required information for a GHG authority made available by the chief executive (Act, s 261(1)(b))—

(a)  for information made available in electronic form, other than on a tape, cartridge or other information storage media

171.90

(b)  for information made available on a tape, cartridge or other information storage media

344.60

Part 6 Amendment of Land Regulation 2020

12Regulation amended

This part amends the Land Regulation 2020.

13Insertion of new s 3A

After section 3
insert—

3ARounding of particular amounts expressed as numbers of fee units

(1)This section applies for working out the amount of a fee or other matter expressed in section 33, 34 or 36 as a number of fee units.
(2)For the purpose of the Acts Interpretation Act 1954, section 48C(3), the amount is to be rounded to the nearest dollar (rounding one-half upwards).

Example—

Section 34(1) of this regulation provides for a minimum rent of 277 fee units. If the value of a fee unit for this regulation were $1.015, the number of dollars obtained by multiplying $1.015 by 277 would be $281.155. After rounding, the amount of the minimum rent would be $281.

14Amendment of s 33 (Rental valuation)

Section 33(3)(b), ‘$13,850’—
omit, insert

13,850 fee units

15Amendment of s 34 (Minimum rent for tenures of particular categories)

(1)Section 34(1), ‘$277’—
omit, insert

277 fee units

(2)Section 34(2), ‘$134’—
omit, insert

134 fee units

16Amendment of s 36 (Rent for tenures of particular categories)

Section 36, table—
omit, insert

Category of tenure
column 1

Amount of rent payable
column 2

category 14.1

134 fee units

category 15.1

134 fee units

category 15.2

6,973 fee units

category 15.3

10,366 fee units

category 15.4

13,952 fee units

category 15.5

20,926 fee units

17Amendment of s 88 (Minimum instalments—Act, ss 457, 462 and 466)

(1)Section 88(2)(a), ‘$379’—
omit, insert

379 fee units

(2)Section 88(2)(b), ‘$940’—
omit, insert

940 fee units

18Replacement of sch 6 (Fees)

Schedule 6
omit, insert

Schedule 6 Fees

section 87

  

Fee units

1

Request for an agreement under section 18 of the Act about a proposed exchange of land (Act, s 18(5))

296.90

2

Application (Act, s 420C(1)(d))—

 
 

(a)  for the allocation of a floating reservation under section 23A(1) of the Act

296.90

 

(b)  to buy land in a reservation under section 24(3) of the Act

296.90

 

(c)  for the dedication of land as a road for public use under section 94(2) of the Act

296.90

 

(d)  for a road closure—
 
 

(i)  if the closure is the permanent closure of the road under section 99(1) of the Act

296.90

 

(ii)  if the closure is the temporary closure of the road under section 99(3) of the Act (including issuing a road licence over the road applied for with the application)

296.90

 

(e)  for the issue of a road licence over a road under section 103(1) of the Act, other than the road licence mentioned in paragraph (d)(ii)

296.90

 

(f)  for the simultaneous opening and closing of roads under section 109A(1) or 109B(1) of the Act

296.90

 

(g)  for the grant of an interest in land under section 120A(1) of the Act

296.90

 

(h)  for the grant of a lease of unallocated State land under section 121(1) of the Act

296.90

 

(i)  for the grant of a deed of grant of unallocated State land under section 122 of the Act

296.90

 

(j)  for a change to a lease—
 
 

(i)  if the change is for the lease to be used for additional or fewer purposes mentioned in section 154(1) of the Act

148.30

 

(ii)  if the change is a change of an imposed condition of the lease mentioned in section 210(2) of the Act

148.30

 

(k)  to extend a lease under section 155A(2) or 155B(2) of the Act

296.90

 

(l)  for an offer of a new lease that is a renewal application under section 158(1) of the Act

296.90

 

(m)  that is an extension application under section 164C(1) of the Act

296.90

 

(n)  that is a conversion application under section 166(1) of the Act

296.90

 

(o)  for approval to subdivide a lease under section 176(1) of the Act

296.90

 

(p)  for approval to amalgamate leases under section 176K(1) of the Act

296.90

 

(q)  for a permit to occupy unallocated State land, a reserve or a road under section 177A(1) of the Act

296.90

 

(r)  for approval to transfer a lease, licence or sublease under section 322(3) of the Act

148.30

 

(s)  for approval to sublease a lease under section 332(1)(a)(i) of the Act

148.30

 

(t)  to amend the description in a lease under section 360C of the Act

148.30

 

(u)  for approval of an easement to be created over land under section 362(1) of the Act

296.90

 

(v)  for approval of a public utility easement to continue over unallocated State land under section 372(2) of the Act

148.30

 

(w)  for approval of a public utility easement that burdens a State lease to continue over a reserve under section 372(3) of the Act

148.30

 

(x)  for approval to make a lease the subject of a profit a prendre under section 373G(1) of the Act

296.90

 

(y)  for a review under section 423 of the Act of an original decision

148.30

3

Issuing—

 
 

(a)  a deed of grant (other than a deed of grant issued under section 18A of the Act because of a surrender of native title, a deed of grant issued to the State or a deed of grant issued under section 358(3)(b) of the Act)

76.85

 

(b)  a lease (other than a lease issued to the State or issued under section 18A of the Act because of a surrender of native title) or licence

76.85

 

(c)  a permit to occupy, other than a permit for a term of less than 3 months issued to a non-profit community organisation

76.85

4

Order in council, under section 216 of the Act, resuming a lease or part of a lease or taking an easement over a lease—

 
 

(a)  for 1 lease or easement or part of a lease or easement

203.70

 

(b)  for each additional lease or easement

99.25

5

Preparing and serving a notice resuming a lease or part of a lease under section 224 of the Act

99.25

6

Document amending an instrument resuming a lease or an easement over a lease

99.25

19Regulation amended

This part amends the Mineral and Energy Resources (Common Provisions) Regulation 2016.

20Replacement of sch 2 (Fees)

Schedule 2
omit, insert

Schedule 2 Fees

section 61

Fee units

1

Lodging a caveat over a resource authority (Act, s 25(1)(c))

139.10

2

Application under section 33(1) of the Act to record associated agreement in the register

52.00

3

Application under section 19 of the Act for approval of a prescribed dealing, other than an assessable transfer—

(a)  for a mining claim under the Mineral Resources Act

52.00

(b)  otherwise

139.10

4

Notifying chief executive under section 19B of the Act of notifiable dealing

52.00

5

Application under section 23 of the Act for an indicative approval for a proposed prescribed dealing that is an assessable transfer—

(a)  for a resource authority, or a share in a resource authority, under the Mineral Resources Act

 

(i)  for a mining claim

52.00

 

(ii)  for an exploration permit—

 

(A)  for coal

390.30

 

(B)  for a mineral other than coal and only if the permit is for not more than 4 sub-blocks in restricted areas 256 to 265

97.60

 

(C)  otherwise

292.80

 

(iii)  for a mineral development licence

778.00

 

(iv)  for a mining lease—

 

(A)  for coal

1,367.00

 

(B)  for corundum, gemstones and other precious stones

238.50

 

(C)  for eluvial, colluvial and alluvial gold and eluvial, colluvial and alluvial tin

238.50

 

(D)  for any other mineral

476.80

(b)  for a resource authority, or a share in a resource authority, under the P&G Act

 

(i)  for an authority to prospect

778.00

 

(ii)  for a petroleum lease, pipeline licence or petroleum facility licence

1,367.00

 

(iii)  otherwise

585.00

(c)  for a resource authority, or a share in a resource authority, under the 1923 Act

 

(i)  for an authority to prospect

778.00

 

(ii)  for a lease

1,367.00

 

(iii)  for a water monitoring authority

585.00

(d)  for a resource authority, or a share in a resource authority, under the Geothermal Act

393.40

(e)  for a resource authority, or a share in a resource authority, under the Greenhouse Gas Act

418.00

6

Application under section 19 of the Act for approval of a prescribed dealing that is an assessable transfer—

(a)  for a resource authority, or a share in a resource authority, under the Mineral Resources Act

 

(i)  for a mining claim

52.00

 

(ii)  for an exploration permit if the Minister has given an indicative approval of the transfer

185.10

 

(iii)  for an exploration permit if the Minister has not given an indicative approval of the transfer—

 

(A)  for coal

575.40

 

(B)  for a mineral other than coal and only if the permit is for not more than 4 sub-blocks in restricted areas 256 to 265

282.70

 

(C)  otherwise

477.90

 

(iv)  for a mineral development licence if the Minister has given an indicative approval of the transfer

185.10

 

(v)  for a mineral development licence if the Minister has not given an indicative approval of the transfer

963.10

 

(vi)  for a mining lease if the Minister has given an indicative approval of the transfer

185.10

 

(vii)  for a mining lease if the Minister has not given an indicative approval of the transfer—

 

(A)  for coal

1,552.10

 

(B)  for corundum, gemstones and other precious stones

423.60

 

(C)  for eluvial, colluvial and alluvial gold and eluvial, colluvial and alluvial tin

423.60

 

(D)  for any other mineral

661.90

(b)  for a resource authority, or a share in a resource authority, under the P&G Act

 

(i)  if the Minister has given an indicative approval of the transfer

185.10

 

(ii)  otherwise—

 

(A)  for an authority to prospect

963.10

 

(B)  for a petroleum lease, pipeline licence or petroleum facility licence

1,552.10

 

(C)  for any other resource authority under the P&G Act

770.10

(c)  for a resource authority, or a share in a resource authority, under the 1923 Act

 

(i)  if the Minister has given an indicative approval of the transfer

185.10

 

(ii)  otherwise—

 

(A)  for an authority to prospect

963.10

 

(B)  for a lease

1,552.10

 

(C)  for a water monitoring authority

770.10

(d)  for a resource authority, or a share in a resource authority, under the Geothermal Act

 

(i)  if the Minister has given an indicative approval of the transfer

185.10

 

(ii)  otherwise

578.50

(e)  for a resource authority, or a share in a resource authority, under the Greenhouse Gas Act

 

(i)  if the Minister has given an indicative approval of the transfer

185.10

 

(ii)  otherwise

603.10

7

Searching and taking extracts from, or obtaining a copy of all or part of a notice, document or information in, the register (Act, s 198(1)(b) and (c))—

(a)  relating to a resource authority under the Mineral Resources Act

 

(i)  for a standard departmental public tenure enquiry report

54.20

 

(ii)  otherwise

54.20

(b)  relating to a resource authority under the P&G Act, 1923 Act or Greenhouse Gas Act

 

(i)  for a standard departmental public tenure enquiry report

54.20

 

(ii)  otherwise

136.00

(c)  relating to a resource authority under the Geothermal Act

 

(i)  for a standard departmental public tenure enquiry report

12.65

 

(ii)  otherwise

29.25

21Regulation amended

This part amends the Mineral Resources Regulation 2013.

22Replacement of sch 4 (Rental payable)

Schedule 4
omit, insert

Schedule 4 Rental payable

section 98(1)

  

Fee units

1

For a mining claim

nil

2

For an exploration permit—for each sub-block to which the exploration permit applies

167.70

3

For a mineral development licence—for each hectare to which the mineral development licence relates—

 
 

(a)  for the first year of the licence

4.65

 

(b)  for the second year of the licence

9.55

 

(c)  for the third year of the licence

14.65

 

(d)  for the fourth year of the licence

25.25

 

(e)  for a year of the licence after the fourth year

30.40

4

For a mining lease—for each hectare to which the mining lease relates

64.80

23Amendment of sch 5 (Fees)

Schedule 5, parts 1 to 7—
omit, insert

Part 1 Prospecting permits

  

Fee units

1

Application for district prospecting permit—for each month of the term of permit applied for (Act, s 21(b)(ii))

136.00

2

Application for parcel prospecting permit (Act, s 21(b)(ii))

136.00

Part 2 Mining claims

  

Fee units

1

Application for grant of mining claim (Act, s 61(1)(j)(iii))

408.40

2

Application for renewal of mining claim (Act, s 93(2)(c))

408.40

3

Application for approval to mine specified minerals not specified in mining claim (Act, s 105(2))

54.20

4

Lodging notice of surrender of mining claim (Act, s 107(1)(c))

54.20

5

Application for variation of the land used or proposed to be used as access in relation to the area of mining claim (Act, s 125(2)(b))

54.20

Part 3 Exploration permits

  

Fee units

1

Application for exploration permit, for a mineral other than coal (Act, s 133(h)(v))—

 
 

(a)  for 4 or fewer sub-blocks in restricted area 256, 257, 258, 259, 260, 261, 262, 263, 264 or 265

340.50

 

(b)  otherwise

1,017.00

2

Tender for exploration permit, for a mineral other than coal (Act, ss 136A(3)(a) and 136E(d)(ii))

1,360.00

3

Tender for exploration permit for coal (Act, s 136E(d)(ii))

1,360.00

4

Application for exploration permit under chapter 4, part 3, division 5 of the Act (Act, s 136R(f)(ii))

1,360.00

5

Application for renewal of exploration permit (Act, s 147(2)(b))—

 
 

(a)  for coal

678.00

 

(b)  for any other mineral—

 

(i)  for 4 or fewer sub-blocks in restricted area 256, 257, 258, 259, 260, 261, 262, 263, 264 or 265

203.90

 

(ii)  otherwise

678.00

6

Application for extension of last renewed term of exploration permit (Act, s 147CA(3)(b)(ii))—

 
 

(a)  for coal

678.00

 

(b)  for any other mineral—

 

(i)  for 4 or fewer sub-blocks in restricted area 256, 257, 258, 259, 260, 261, 262, 263, 264 or 265

203.90

 

(ii)  otherwise

678.00

Part 4 Mineral development licences

  

Fee units

1

Application for mineral development licence (Act, s 183(1)(n)(iii))—

 
 

(a)  for coal

2,724.00

 

(b)  for any mineral other than coal

2,724.00

2

Application for renewal of mineral development licence (Act, s 197(2)(b))—

 
 

(a)  for coal

952.00

 

(b)  for any mineral other than coal

952.00

3

Application for adding stated minerals to mineral development licence (Act, s 208(2))

678.00

4

Lodging notice of surrender of mineral development licence (Act, s 210(3)(c))

203.90

5

Application for variation of the land used or proposed to be used as access in relation to the area of mineral development licence (Act, s 231(2)(b))

476.70

Part 5 Mining leases

  

Fee units

1

Obtaining copy of mining lease application (s 20(2))

54.20

2

Application for grant of mining lease (Act, s 245(1)(p)(iii))—

 
 

(a)  for coal

4,767.00

 

(b)  for corundum, gemstones and other precious stones

849.00

 

(c)  for eluvial, colluvial and alluvial gold and eluvial, colluvial and alluvial tin

849.00

 

(d)  for any other mineral

1,699.00

3

Application for surface of restricted land for mining lease to be included in the lease (Act, s 275A(3))

476.70

4

Application for renewal of mining lease (Act, s 286(2)(b))—

 
 

(a)  for coal

4,767.00

 

(b)  for corundum, gemstones and other precious stones

849.00

 

(c)  for eluvial, colluvial and alluvial gold and eluvial, colluvial and alluvial tin

849.00

 

(d)  for any other mineral

1,699.00

5

Application for approval to mine specified minerals (other than coal seam gas) not specified in mining lease (Act, s 298(2))

678.00

6

Application to add a purpose (other than mining of minerals) to mining lease granted for purposes other than the mining of minerals (Act, s 298(5))

678.00

7

Application to add a purpose to mining lease granted for mining of minerals (Act, s 298(7))

678.00

8

Application for grant of mining lease consolidating mining leases other than coal mining leases or oil shale mining leases (Act, s 299(2))

678.00

9

Lodging notice of surrender of mining lease (Act, s 309(2)(c))

203.90

10

Application for variation of the land used or proposed to be used as access in relation to the area of mining lease (Act, s 317(2)(b))

476.70

11

Application for indicative approval of an application transfer (Act, s 318AAR(2)(c)(ii))—

 
 

(a)  for coal

1,367.00

 

(b)  for corundum, gemstones and other precious stones

238.50

 

(c)  for eluvial, colluvial and alluvial gold and eluvial, colluvial and alluvial tin

238.50

 

(d)  for any other mineral

476.80

12

Application for approval of an application transfer (Act, s 318AAS(2)(c))—

 
 

(a)  if the Minister has given an indicative approval of the transfer

185.10

 

(b)  otherwise—
 
 

(i)  for coal

1,552.10

 

(ii)  for corundum, gemstones and other precious stones

423.60

 

(iii)  for eluvial, colluvial and alluvial gold and eluvial, colluvial and alluvial tin

423.60

 

(iv)  for any other mineral

661.90

Part 6 Fees relating to chapter 8 of the Act

  

Fee units

1

Application for amendment of relinquishment condition (Act, s 318DC(g))

1,360.00

2

Application for grant of mining lease consolidating coal mining leases or oil shale mining leases (Act, s 318DM(2)(b))

1,360.00

3

Lodging proposed later development plan for coal or oil shale mining lease within the time required under section 318EB(3) of the Act (Act, s 318EB(6), definition relevant fee, paragraph (a))

1,360.00

Part 7 Water monitoring bores

  

Fee units

1

Transfer of water monitoring bore to landowner (Act, s 334ZZO(1)(b))

2,039.00

2

Transfer of water monitoring bore to holder of mineral development licence, mining lease or water monitoring authority (Act, s 334ZZQ(1)(c))

2,039.00

24Regulation amended

This part amends the Petroleum and Gas (General Provisions) Regulation 2017.

25Amendment of s 64 (Fees generally)

Section 64(1), after ‘in’—
insert—

section 66A and

26Insertion of new s 66A

After section 66
insert—

66AAnnual fee that is proportion of cost of State’s funding commitments to national energy market regulation

For the 2004 Act, section 423(3), the annual fee payable by a pipeline licence holder that is a proportion of the cost of the State’s funding commitments to national energy market regulation is $315.34 for each kilometre of pipeline the subject of the licence.

27Amendment of s 67 (Application of division)

Section 67(a)—
omit, insert—
(a)the following fees (each an annual fee)—
(i)an annual fee payable by a pipeline licence holder under the 2004 Act, section 423(3) that is a proportion of the cost of the State’s funding commitments to national energy market regulation;
(ii)an annual fee stated in schedule 2 for a pipeline licence or petroleum facility licence; and

28Replacement of schs 2–4

Schedules 2 to 4
omit, insert—

Schedule 2 Fees payable under 2004 Act

section 64(1)

Part 1 Petroleum tenure fees

  

Fee units

1

Tender for authority to prospect (2004 Act, s 37(d)(i))

2,724.00

2

Application for approval to amend the work program for an authority to prospect (2004 Act, s 60(4))

1,360.00

3

Lodging a proposed later work program for an authority to prospect within the time required under the 2004 Act, section 79(3) (2004 Act, s 79(6), definition relevant fee, paragraph (a))

1,360.00

4

Application for renewal of authority to prospect (2004 Act, s 82(1)(h)(i))

2,724.00

5

For a declaration that all or a stated part of the area of an authority to prospect is a potential commercial area for the authority—

 

(a)  application for the declaration (2004 Act, s 89(2)(b))

2,039.00

(b)  application for extension of the term of the declaration (2004 Act, s 93(2))

2,039.00

6

Application to divide an authority to prospect (2004 Act, s 104(g))

2,039.00

7

Application to amalgamate 2 or more potential commercial areas for an authority to prospect (2004 Act, s 107AB(d))

2,039.00

8

Application for approval of a special amendment (2004 Act, s 107A(4))

1,360.00

9

ATP-related application for a petroleum lease (2004 Act, s 118(f))

4,767.00

10

Lodging a proposed later development plan for a petroleum lease within the time required under the 2004 Act, section 159(3) (2004 Act, s 159(6), definition relevant fee, paragraph (a))

1,360.00

11

Application for renewal of petroleum lease (2004 Act, s 162(1)(f)(i))

4,767.00

12

Application to amalgamate 2 or more petroleum leases (2004 Act, s 170C(c))

4,767.00

13

Application to divide petroleum lease (2004 Act, s 172(g))

4,767.00

14

Application to change production commencement day for petroleum lease to a new day (2004 Act, s 175AB(1)(d))

6,391.00

15

Notice of claim of ownership of stored petroleum or prescribed storage gas (2004 Act, s 213(2)(c))

1,360.00

16

Application for approval of proposed coordination arrangement (2004 Act, s 235(2)(b)(ii))

2,039.00

17

Application for amendment of relinquishment condition (2004 Act, s 372(1)(g))

1,360.00

Part 2 Data acquisition authority and water monitoring authority fees

  

Fee units

1

Application for data acquisition authority (2004 Act, s 177(b))

2,039.00

2

Application for water monitoring authority (2004 Act, s 191(b))

2,039.00

3

Application to amend water monitoring authority (2004 Act, s 203(3)(b))

2,039.00

Part 3 Transfer fees

  

Fee units

1

Transfer of bore in the area of a petroleum tenure to the landowner (2004 Act, s 288(3)(b))

2,039.00

2

Transfer of petroleum well in the area of a petroleum tenure to the holder of a geothermal tenure or mining tenement (2004 Act, s 289(b))

2,039.00

3

Transfer of water observation bore in the area of a petroleum tenure or water monitoring authority to the holder of another petroleum tenure or water monitoring authority (2004 Act, s 290(1)(b))

2,039.00

Part 4 Survey licence, pipeline licence and petroleum facility licence fees

  

Fee units

1

Application for survey licence (2004 Act, s 395(2)(d))

678.00

2

Application for pipeline licence (2004 Act, s 409(f))

4,767.00

3

Handling fee to record information about completion of pipeline (2004 Act, s 420(3)(d))

203.90

4

Annual licence fee for pipeline licence (2004 Act, s 423(1))—

 
 

(a)  for a point-to-point pipeline licence (for each kilometre of the pipeline the subject of the licence)

162.10

 

(b)  for an area pipeline licence (for each kilometre of the pipeline the subject of the licence)

40.15

5

Application for petroleum facility licence (2004 Act, s 445(e))

4,767.00

6

Annual licence fee for petroleum facility licence (2004 Act, s 454(1))—

 
 

(a)  if the petroleum facility land for the licence is 2km2 or less

3,247.00

 

(b)  if the petroleum facility land for the licence is more than 2km2 (for each square kilometre of the petroleum facility land)

1,621.00

7

Application for a part 5 permission (2004 Act, s 464(b))

1,017.00

8

Application to amend licence (2004 Act, s 475(b))

2,039.00

9

Application for renewal of licence other than a survey licence (2004 Act, s 480(c)(i))

2,039.00

Part 5 General petroleum authority fees

  

Fee units

1

Fee for required information for a petroleum tenure made available by the chief executive (2004 Act, s 550(1)(b))—

 
 

(a)  for information made available in electronic form, other than on a tape or cartridge

184.70

 

(b)  for information made available on a tape or cartridge

369.70

2

Application for approval of surrender of petroleum authority other than an authority to prospect (2004 Act, s 576(1)(b))

1,017.00

Schedule 3 Fees payable under 1923 Act

section 64(2)

Part 1 Petroleum tenure fees

  

Fee units

1

Application for renewal of lease (1923 Act, s 45(2A)(c)(i))

4,767.00

2

Application for consent to surrender and terminate lease (1923 Act, s 52(1B)(b)(i))

1,017.00

3

Lodging a proposed later work program for an authority to prospect within the time required under the 1923 Act, section 74K(3) (1923 Act, s 74K(6), definition relevant fee, paragraph (a))

1,360.00

4

Lodging a proposed later development plan for a lease within the time required under the 1923 Act, section 74Q(3) (1923 Act, s 74Q(6), definition relevant fee, paragraph (a))

1,360.00

5

Application for amendment of relinquishment condition (1923 Act, s 77T(1)(g))

1,360.00

Part 2 Transfer fees

  

Fee units

1

Transfer of water observation bore or water supply bore in the area of a 1923 Act petroleum tenure to the landowner (1923 Act, s 75Q(3)(b))

2,039.00

2

Transfer of well in the area of a 1923 Act petroleum tenure to the holder of a geothermal tenure or mining tenement (1923 Act, s 75R(b))

2,039.00

3

Transfer of water observation bore in the area of a 1923 Act petroleum tenure to the holder of another 1923 Act petroleum tenure, 2004 Act petroleum tenure or water monitoring authority (1923 Act, s 75S(1)(b))

2,039.00

Part 3 Other fees

  

Fee units

1

Fee for required information for a 1923 Act petroleum tenure made available by the chief executive (1923 Act, s 76D(1)(b))—

 
 

(a)  for information made available in electronic form, other than on a tape or cartridge

184.70

 

(b)  for information made available on a tape or cartridge

369.70

Schedule 4 Rent

sections 65 and 66

Part 1 Annual rent

  

Fee units

1

Annual rent for authority to prospect under the 2004 Act (for each sub-block included in the area for the authority) (2004 Act, s 75(1)(b))

3.00

2

Annual rent for petroleum lease under the 2004 Act (for each square kilometre of the area for the lease) (2004 Act, s 155(1)(b))

162.00

3

Annual rent for data acquisition authority (for each sub-block included in the area of the authority) (2004 Act, s 184A(1))

3.00

4

Annual rent for water monitoring authority (for each sub-block included in the area of the authority) (2004 Act, s 202A(1))

1.51

5

Annual rent for a lease under the 1923 Act (for each square kilometre of the area for the lease) (1923 Act, s 46(1))

162.00

6

Annual rent for an authority to prospect under the 1923 Act (for each sub-block included in the area for the authority) (1923 Act, s 74N(1)(b))

3.00

Part 2 Storage rent

  

Fee units

1

Annual rent for storing petroleum or prescribed storage gas as mentioned in the 2004 Act, section 212(1)(b) (2004 Act, s 227(3)) for each square kilometre of—

 

(a)  the area of the old lease, unless paragraph (b) applies

162.00

 

(b)  for a proposed petroleum lease the area of which includes the reservoir where the petroleum is stored, if the Minister has made a call for tenders under the 2004 Act, section 218—the area of the proposed petroleum lease stated in the call for tenders

162.00

29Regulation amended

This part amends the Stock Route Management Regulation 2003.

30Replacement of sch 2 (Fees)

Schedule 2
omit, insert—

Schedule 2 Fees

section 17(1)

  

Fee units

1

Permit fee for stock route agistment permit (Act, s 116(5))—

 
 

(a)  for large stock—
 
 

(i)  minimum fee, for each head, for each week

1.22

 

(ii)  maximum fee, for each head, for each week

2.95

 

(b)  for small stock—
 
 

(i)  minimum fee, for each head, for each week

0.113

 

(ii)  maximum fee, for each head, for each week

0.465

2

Permit fee for stock route travel permit (Act, s 134(3))—

 
 

(a)  for large stock—for each kilometre, for each 20 head or part of 20 head

0.0242

 

(b)  for small stock—for each kilometre, for each 100 head or part of 100 head

0.0242

3

Inspecting register of water facility agreements (Act, s 164(3)(a))

17.05

Part 11 Amendment of Surveyors Regulation 2014

31Regulation amended

This part amends the Surveyors Regulation 2014.

32Replacement of sch 1 (Fees)

Schedule 1
omit, insert

Schedule 1 Fees

section 8

  

Fee units

1

Registration or registration endorsement, for an individual (Act, s 45(1)(c)(i) and (ii))—

 
 

(a)  registration as a surveyor—
 
 

(i)  application fee

187.20

 

(ii)  registration fee

232.40

 

(b)  registration endorsement as a consulting surveyor—
 
 

(i)  application fee

187.20

 

(ii)  registration fee

283.50

 

(c)  registration endorsement, other than as a consulting surveyor—
 
 

(i)  application fee

85.05

 

(ii)  registration fee

34.00

 

(d)  registration as a surveying graduate—
 
 

(i)  application fee

187.20

 

(ii)  registration fee

187.20

 

(e)  registration as a surveying associate—
 
 

(i)  application fee

187.20

 

(ii)  registration fee

170.10

 

(f)  registration as an emeritus surveyor—
 
 

(i)  application fee

90.75

 

(ii)  registration fee

nil

2

Registration or registration endorsement, for a corporation (Act, s 45(1)(c)(i) and (ii))—

 
 

(a)  registration as a surveyor with a registration endorsement as a consulting surveyor—
 
 

(i)  application fee

453.60

 

(ii)  registration fee

993.00

 

(b)  registration endorsement, other than as a consulting surveyor—
 
 

(i)  application fee

85.05

 

(ii)  registration fee

34.00

3

Renewal of registration or registration endorsement, for an individual (Act, s 54(2)(c)(ii) and (3))—

 
 

(a)  registration as a surveyor—
 
 

(i)  registration fee

232.40

 

(ii)  late application fee

85.05

 

(b)  registration endorsement as a consulting surveyor—
 
 

(i)  registration fee

283.50

 

(ii)  late application fee

nil

 

(c)  registration endorsement, other than as a consulting surveyor—
 
 

(i)  registration fee

34.00

 

(ii)  late application fee

nil

 

(d)  registration as a surveying graduate—
 
 

(i)  registration fee

187.20

 

(ii)  late application fee

85.05

 

(e)  registration as a surveying associate—
 
 

(i)  registration fee

170.10

 

(ii)  late application fee

85.05

 

(f)  registration as an emeritus surveyor—
 
 

(i)  registration fee

nil

 

(ii)  late application fee

nil

4

Renewal of registration or registration endorsement, for a corporation (Act, s 54(2)(c)(ii) and (3))—

 
 

(a)  registration fee for registration as a surveyor with a registration endorsement as a consulting surveyor

993.00

 

(b)  registration fee for registration endorsement, other than as a consulting surveyor

34.00

 

(c)  late application fee

283.50

5

Restoration of registration or registration endorsement (Act, s 60(1)(b)(i))—application fee (in addition to any fees payable under item 3 or 4)

135.90

6

Replacement or duplicate registration certificate (Act, s 78(2)(b))

96.45

7

Assessment fee for an application for competency assessment (Act, s 44(2))—

 
 

(a)  if the competency assessment involves assessing a professional assessment project—
 
 

(i)  lodging the application

187.20

 

(ii)  assessing the project

538.00

 

(b)  if the competency assessment involves reassessing a professional assessment project—
 
 

(i)  lodging the application

187.20

 

(ii)  reassessing the project

340.20

 

(c)  if the competency assessment involves assessing a person’s competence equivalence for registration or registration endorsement as a surveyor—
 
 

(i)  lodging the application

187.20

 

(ii)  assessing the person’s competence equivalence

964.00

33Regulation amended

This part amends the Valuation of Land Regulation 2003.

34Amendment of s 7 (Fee for copy of valuation roll—Act, s 203)

Section 7(1)(a), ‘$6,239’—
omit, insert—

6,239 fee units

35Amendment of s 8 (Fee for making valuation—Act, s 209)

Section 8(2), ‘$92’—
omit, insert—

92 fee units

36Replacement of schs 1 and 2

Schedules 1 and 2
omit, insert

Schedule 1 Fee for copy of valuation roll

section 7(1)(b)

  

Fee units

1

Business or multi-unit—for each valuation of a parcel of rateable land used or occupied

18.15

2

Other than business or multi-unit—for each valuation of a parcel of rateable land used or occupied if the area is—

 
 

(a)  less than 4,000m2

7.75

 

(b)  4,000m2 or more, but less than 20ha

8.10

 

(c)  20ha or more, but less than 40ha

11.60

 

(d)  40ha or more, but less than 200ha

15.50

 

(e)  200ha or more

21.70

Schedule 2 Fees

section 9

  

Fee units

1

Copy of certificate of valuation

37.65

2

Certified copy of—

 
 

(a)  an extract of an entry on a valuation roll

37.65

 

(b)  an ownership change notice (including the search fee)

37.65

3

Payable by a local government for—

 
 

(a)  amendment of a valuation to be used for making and levying rates under section 87, 88 or 100 of the Act

40.00

 

(b)  making a valuation under section 83(1)(a) of the Act of land in its local government area

40.00

4

Searching for particulars contained in—

 
 

(a)  an entry on the current valuation roll—
 
 

(i)  at an office of the department

18.65

 

(ii)  using electronic access

14.90

 

(b)  a notice under section 245 of the Act held on the current valuation roll—
 
 

(i)  at an office of the department

18.65

 

(ii)  using electronic access

14.90

 

(c)  an entry on a valuation roll, other than the current valuation roll

29.85

 

(d)  a notice under section 245 of the Act held on a valuation roll, other than the current valuation roll

29.85

 

(e)  an entry on a valuation roll, supplied in the form of a computer listing—
 
 

(i)  for each entry

1.06

 

(ii)  minimum fee for each listing

144.30

5

For particulars contained in a notice under section 245 of the Act—

 
 

(a)  given in an abbreviated form—for each entry

9.30

 

(b)  given as an entry in a copy of a monthly computer listing—
 
 

(i)  for each entry

1.06

 

(ii)  for a consolidated listing of entries already supplied in a monthly computer listing—for each 100 entries

7.80

 

(iii)  minimum fee for each listing, other than a consolidated listing

144.30

37Regulation amended

This part amends the Valuers Registration Regulation 2013.

38Replacement of sch 2 (Fees)

Schedule 2
omit, insert

Schedule 2 Fees

section 6

  

Fee units

1

Application for registration as a valuer (Act, s 29(1)(c))

253.30

2

Certificate of registration (Act, s 34(1))

72.70

3

Roll fee (Act, s 36(1))

253.30

4

Late fee (Act, s 36(2))

72.70

5

Late fee (Act, s 36B(2))

72.70

6

Application for restoration of registration as a valuer (Act, s 40(2))

253.30

7

Application to be recorded as a specialist retail valuer (Act, s 42B(2))

253.30

8

Renewal of recording as a specialist retail valuer on the list kept by the board (Act, s 42FA(a))

253.30

9

Application for restoration of valuer’s particulars on list of specialist retail valuers (Act, s 42GB(2)(b))

72.70

39Regulation amended

This part amends the Vegetation Management Regulation 2012.

40Replacement of sch 7 (Fees)

Schedule 7
omit, insert

Schedule 7 Fees

section 12

  

Fee units

1

Application for making a PMAV (Act, s 20C(2)(c))

475.50

2

Preparing a restoration plan (Act, s 55AB(4))—

 
 

(a)  if a field visit is not required

967.00

 

(b)  if a field visit is required

4,153.00