QueenslandAcquisitionofLandAct1967Current as at 1 July 2013
Information about this reprintThis
reprint shows the legislation current as at the date on the cover
and is authorised bythe Parliamentary Counsel.AnewreprintofthelegislationwillbepreparedbytheOfficeoftheQueenslandParliamentary
Counsel when any change to the legislation takes effect. This
change maybe because a provision of the original
legislation, or an amendment to it, commences orbecause a particular provision of the
legislation expires or is repealed.When a new reprint
is prepared, this reprint will become a historical reprint. Also,
if it isnecessary to replace this reprint before a
new reprint is prepared, for example, to includeamendments with a retrospective commencement,
an appropriate note would be includedonthecoverofthereplacementreprintandonthecopyofthisreprintatwww.legislation.qld.gov.au.The
endnotes to this reprint contain detailed information about the
legislation and reprint.For example—•The
table of reprints endnote lists any previous reprints and, for this reprint, givesdetails of any discretionary editorial powers under theReprints Act 1992used by theOffice of the Queensland Parliamentary Counsel in preparing it.•Thelistoflegislationendnotegiveshistoricalinformationabouttheoriginallegislationandthelegislationwhichamendedit.Italsogivesdetailsofuncommencedamendmentstothislegislation.Forinformationaboutpossibleamendments to the
legislation by Bills introduced in Parliament, see the
QueenslandLegislationCurrentAnnotationsatwww.legislation.qld.gov.au/Leg_Info/information.htm.•The
list of annotations endnote gives historical information at section
level.All Queensland reprints are dated and
authorised by the Parliamentary Counsel. Theprevious numbering
system and distinctions between printed and electronic reprints
arenot continued.
Acquisition of Land Act 1967Acquisition of Land Act 1967Part 1
Preliminary[s 1][as amended by
all amendments that commenced on or before 1 July 2013]AnActtoconsolidateandamendthelawrelatingtotheacquisition of land for public works
and other public purposes,and for other purposesPart
1Preliminary1Short
titleThis Act may be cited as theAcquisition of Land Act 1967.2DefinitionsThe dictionary
in schedule 2 defines particular words used inthis Act.3Meaning ofmulti-parcel
purpose(1)Land is taken under this Act for
amulti-parcel purposeif, tocarry out the particular purpose for which
the land is taken, itisnecessarytotake,underthisAct,morethan1parcelofland.Examples of
multi-parcel purposes—roads and
railways for which it is necessary to take, under this Act,
morethan 1 parcel of land(2)For
subsection (1), it does not matter whether—(a)theparcelsoflandareownedbythesamepersonordifferent persons; orCurrent as at 1 July 2013Page
5
Acquisition of Land Act 1967Part 1
Preliminary[s 4](b)the
same person or different persons are entitled to claimcompensationunderthisActforthetakingoftheparcels of
land.(3)In this section—parcel, of
land, means—(a)a separate lot or parcel in a plan of
survey registered, ordeposited for registration, in the
land registry or given tothe chief executive (surveys);
or(b)an easement; or(c)other land that is described in a way that
is sufficient tosubstantially identify the land.4Relationship with other Acts(1)ThissectionappliesifanotherActprovidesforlandtobetakenunderthisAct,eventhoughthisActwouldnototherwise apply to the land.Example—TheNative Title (Queensland) Act
1993provides for native title rightsand
interests relating to land, for example, unallocated State land
undertheLand Act 1994, to be acquired
under this Act even though this Actwould not
otherwise apply to unallocated State land.(2)Despite the other Act, sections 9(7) and 15D
do not apply tothetakingoflandifthelandincludesAboriginalorTorresStrait
interests.(3)For subsection (2), land includes
Aboriginal or Torres StraitIslander
interests if—(a)native title rights and interests
exist for the land; or(b)the land is
Aboriginal land or transferable land under theAboriginal Land
Act 1991; or(c)thelandisTorresStraitIslanderlandortransferableland under
theTorres Strait Islander Land Act 1991.Page 6Current as at 1
July 2013
Part
2Acquisition of Land Act 1967Part 2
Taking of land[s 5]Taking of
landDivision 1General5Purposes for which land may be
taken(1)Land may be taken under and subject to
this Act—(a)where the constructing authority is
the Crown, for anypurpose set out in schedule 1; or(b)wheretheconstructingauthorityisalocalgovernment—(i)foranypurposesetoutinschedule1whichthelocal government may lawfully carry out;
or(ii)foranypurpose,includinganyfunctionoflocalgovernment,whichthelocalgovernmentisauthorisedorrequiredbyaprovisionofanActother than this
Act to carry out; or(c)inthecaseofaconstructingauthorityotherthantheCrown or a local government—(i)foranypurposesetoutinschedule1whichthatconstructing authority may lawfully carry
out; or(ii)for any purpose
which that constructing authorityis authorised or
required, by a provision of an Actother than this
Act, to carry out.(2)The power to take, under and subject
to this Act, land for apurpose (theprimary
purpose) includes power to take fromtime
to time as required land either for the primary purpose orfor
any purpose incidental to the carrying out of the primarypurpose.(3)The
Governor in Council, pursuant to any powers under theLand
Act 1994to resume land, at the request of a
constructingauthorityotherthantheCrown,maytakeonitsbehalfanyland
comprised in a lease or any easement on a lease withinthemeaningofthatActrequiredbysuchconstructingCurrent as at 1
July 2013Page 7
Acquisition of Land Act 1967Part 2
Taking of land[s 6]authorityforapurposeforwhichitmaytakeunderandsubject to this Act land or an
easement on land granted in feesimple.Note—See theLand
Act 1994,chapter 5, part 3 for the resumption of
leases oreasements under that Act.(4)The heading to a part of schedule 1 in
which a purpose fortakinglandissetoutindicatesonlythetypeofactivityorother thing to which the purpose ordinarily
relates and doesnot limit the matters to which the purpose
may relate.6Easements(1)When
for any purpose it is not necessary that the constructingauthority should take the whole estate in
any land, but it issufficientforsuchpurposetotakeaneasement,theconstructing authority may take such
easement only and forthat purpose the provisions of this
Act shall apply as if theeasement were land.(2)Uponapplicationinthatbehalf,paymentoftheprescribedfees,andtheproductiontothelandregistryofthegazettecopy
of the gazette resumption notice, whereby an easementistakenaffectinglandundertheLandTitleAct1994,theregistrar of titles shall register
such easement as prescribed bythatAct,notwithstandingthatsucheasementisnotbeingannexed to or used and enjoyed together with
any other land.(3)The taking of an easement over land
does not extinguish anyinterest in the land existing
immediately before the easementis taken.Division 2Taking other
than by agreement7Notice of intention to take
land(1)A constructing authority which
proposes to take any land shallserveasprescribedbythissectionthenotice(anoticeofintention to resume) prescribed by
this section.Page 8Current as at 1
July 2013
Acquisition of Land Act 1967Part 2
Taking of land[s 7](2)A
notice of intention to resume shall be served upon any andeverypersonwhototheknowledgeoftheconstructingauthority—(a)will
be entitled to claim compensation under this Act inrespect of the taking of the land concerned;
or(b)is a mortgagee of the land.(2A)Despite
subsection (2), if the land the subject of a notice ofintention to resume is common property
within the meaningof,andshownonabuildingunitsplanunder,theBuildingUnitsandGroupTitlesAct1980, the
constructing authorityneed only serve the notice on—(a)thebodycorporateconstitutedunderthatActbytheproprietors of
the lots in the building units plan; and(b)each
entity, other than the body corporate or a proprietorof a
lot in the building units plan on which the commonpropertyisshown,whototheknowledgeoftheconstructingauthorityhasaninterestinthecommonproperty.(2B)Also
despite subsection (2), if the land the subject of a noticeof
intention to resume is common property for a communitytitlesschemeundertheBodyCorporateandCommunityManagementAct1997, the
constructing authority need onlyserve the notice
on—(a)thebodycorporateunderthatActforthecommunitytitles scheme; and(b)each
entity, other than the body corporate or an owner ofalotinthecommunitytitlesschemeforthecommonproperty,whototheknowledgeoftheconstructingauthority has an
interest in the common property.(2C)Subsection (2D) applies if the constructing
authority gives abody corporate mentioned in subsection (2A)
or (2B) a noticeofintentiontoresumeoranoticeamendinganoticeofintention to resume (each arelevant notice).(2D)The body
corporate must ensure a copy of the relevant noticeaccompanies the first notice of a general
meeting of the bodyCurrent as at 1 July 2013Page
9
Acquisition of Land Act 1967Part 2
Taking of land[s 7]corporategiventoeachofitsmembersafterreceivingtherelevant notice.(3)A
notice of intention to resume shall be in writing and shall—(a)statetheparticularpurposeforwhichthelandtobetaken is required; and(b)statethedescriptionofthelandtobetakenwhichdescription—(i)if
the land is described as a separate lot or parcel ina
plan of survey registered in the land registry ordepositedintheofficeofthechiefexecutive(surveys)—shall be that description;
or(ii)ifthelandisnotdescribedasmentionedinsubparagraph(i)—maybemadeinanymannersufficient to
substantially identify the land; and(c)inthecaseofaneasement—alsostatetherightsandobligationstobeconferredandimposedbytheeasement; and(d)state that the person to whom the notice is
directed may,on or before the date specified in the
notice (being a datenot less than 30 days after the date
of the notice), serveupon the constructing authority at the
address set out inthenoticeanobjectioninwritingtothetakingoftheland; and(e)inrelationtotheobjectionmentionedinparagraph(d)—set
out—(i)thattheobjectionmuststatethegroundsoftheobjection and the facts and
circumstances relied onby the objector in support of those
grounds; and(ii)thatanymatterpertainingtotheamountorpaymentofcompensationisnotagroundofobjection; and(iii)that
an objector who states in the objection that theobjectordesirestobeheardinsupportofthegrounds of the objection may appear
and be heardPage 10Current as at 1
July 2013
Acquisition of Land Act 1967Part 2
Taking of land[s 7]by the
constructing authority or its delegate at thetime and place
specified in the notice; and(ea)if
the land the subject of the notice is common propertywithin the meaning of, and shown on a
building unitsplanunder,theBuildingUnitsandGroupTitlesAct1980—(i)statetheproprietorofalotinthebuildingunitsplan
may be entitled to compensation for damagesuffered by the
proprietor as a result of the takingofthecommonpropertyandtheeffectofthetaking on the
proprietor’s lot; and(ii)statetherequirementimposedonthebodycorporateforthecommonpropertyundersubsection (2D);
and(eb)if the land the
subject of the notice is common propertyforacommunitytitlesschemeundertheBodyCorporate and
Community Management Act 1997—(i)statetheownerofalotintheschememaybeentitledtocompensationfordamagesufferedbythe owner as a result of the taking of
the commonproperty and the effect of the taking on the
owner’slot; and(ii)statetherequirementimposedonthebodycorporateforthecommonpropertyundersubsection (2D);
and(f)statethattheconstructingauthorityiswillingtonegotiate to acquire by agreement or,
failing agreement,totreatastothecompensationtobepaidandallconsequential matters; and(g)include details of—(i)the period within which a claim for
compensationunder this Act must be served on the
constructingauthority; andCurrent as at 1
July 2013Page 11
Acquisition of Land Act 1967Part 2
Taking of land[s 7](ii)the
claimant’s right to apply to the Land Court toserve a claim
after the end of the period mentionedin subparagraph
(i); andNote—For the matters
mentioned in paragraph (g), see section 19(3) to(6).(h)include information about how, under section
20(2A), acontract,licence,agreementorotherarrangemententeredintoinrelationtothelandafterthenoticeofintentiontoresumeisservedmaybedealtwithinassessing compensation to be paid
under this Act.Note—See also—(a)theGeothermal Energy
Act 2010, section 350A(8) for additionalrequirements if geothermal interests under
that Act are to be whollyor partially extinguished; and(b)theGreenhouseGasStorageAct2009,section369A(8)foradditional requirements if GHG interests
under that Act are to bewholly or partially extinguished;
and(c)theMineral Resources
Act 1989, section 10AAA(8) for additionalrequirements if mining tenement interests
under that Act are to bewholly or partially extinguished;
and(d)thePetroleumAct1923,section124A(8)foradditionalrequirements if
1923 Act petroleum interests under that Act are tobe
wholly or partially extinguished; and(e)thePetroleum and Gas (Production and
Safety) Act 2004,section30AA(8) for
additional requirements if petroleum interests underthat
Act are to be partially or wholly extinguished.(4)Where a notice of intention to resume
relates to land under theLandTitleAct1994,theconstructingauthorityshallfileacopy of the notice with the land
registry.(4AA)Theconstructingauthoritymay,bywrittennoticegiventoeachentitytowhomthenoticeofintentiontoresumeisserved under subsection (2), (2A) or (2B),
amend the notice ofintention to resume.(4AB)If
the constructing authority amends the notice of intention toresume, the period within which an entity
may serve on thePage 12Current as at 1
July 2013
Acquisition of Land Act 1967Part 2
Taking of land[s 7]constructing
authority an objection to the taking of the landstarts again from the day the notice of the
amendment is givento the entity.Note—Fortheperiodwithinwhichanentitymayserveanobjection,seesubsection (3)(d).(4A)If
the constructing authority amends the notice of intention toresume or discontinues the resumption it
shall forthwith filewiththelandregistryanoticeoftheamendmentordiscontinuance.(4B)Forthepurposeofsubsection(4A),notwithstandingthataconstructing authority has not served
notice under section 16,itshallbedeemedtodiscontinuearesumptioniftheapplicationprescribedbysection9(3)hasnotbeenmadewithin the time
prescribed by section 9(4).(5)Thefailurebytheconstructingauthoritytoserveupontheowner a notice of intention to resume,
where such failure isdue to circumstances beyond the
control of the constructingauthority, or
the failure of the constructing authority to serveupon
any person other than the owner a notice of intention toresume, or the failure of the constructing
authority to observesubsection(4),shallnotprejudiceanygazetteresumptionnotice made
under this Act, with respect to any land, and anyland
included in the notice shall be taken in terms of the noticenotwithstandinganysuchfailure,andthefailurebytheconstructingauthoritytoserveuponanypersonentitledtheretoanynoticeasprescribedbythisActshallnotinvalidatethecontinuanceordiscontinuanceofanyresumption.(6)In
subsection (5)—ownermeans,inthecaseoflandundertheLandTitleAct1994, the person
registered as the proprietor in fee simple atthe date of the
notice of intention to resume.Current as at 1
July 2013Page 13
Acquisition of Land Act 1967Part 2
Taking of land[s 8]8Dealing with
objections(1)A person entitled to be served with a
notice of intention toresume land who has objected as
prescribed to the taking (theobjector)
shall not be entitled to be heard in support of thegroundsoftheobjectionunlessthepersonstatedintheobjection that
the person desired to be so heard and appears,inpersonorbycounsel,solicitororagent,atthetimeandplace specified in the notice.(2)Theconstructingauthorityshallconsiderthegroundsofobjection to the taking of any land
and—(a)iftheobjectorhasbeenheardbytheconstructingauthority—themattersputforwardbytheobjectorinsupport of such grounds; or(b)iftheobjectorhasbeenheardbythedelegateoftheconstructingauthority—thereportthereonofsuchdelegate.(2A)Ifuponsuchconsideration,theconstructingauthorityisofopinion that the
resumption should be discontinued or that thenoticeofintentiontoresumeshouldbeamended,theconstructingauthoritymaydiscontinuetheresumptionoramend the notice of intention to
resume.(2B)However,anoticeofintentiontoresumeshallnotbeamended so as to
include therein land additional to the landthe subject
thereof.(3)If the constructing authority amends
the notice of intention toresume, the objector can not again
object to the taking of theland as provided
for under the amended notice if the owner ofthe land
(whether or not the owner is the objector) agrees tothe
amendment.9Ways in which land is to be
taken(1)If within the time stated in the
notice of intention to resume noobjectionismadeorif,afterdueconsiderationofallobjections,theconstructingauthorityisofopinionthatthelandinquestionisrequiredforthepurposeforwhichitisPage 14Current as at 1
July 2013
Acquisition of Land Act 1967Part 2
Taking of land[s 9]proposed to be
taken, the constructing authority may apply tothe relevant
Minister that the land be taken as prescribed bythis
section.(2)Suchapplicationshallbemadewithin12monthsafterthedate of the notice of intention to
resume and not thereafter.(3)Such application
shall contain or be accompanied by each ofthe
following—(a)a copy of the relevant notice of
intention to resume andof any further notice amending the
same served undersection 7;(b)where the land is not described in the
notice of intentionto resume as mentioned in section
7(3)(b)(i)—a copy ofa plan of survey of the land certified
as accurate by acadastralsurveyororaplansufficienttosubstantiallyidentify the
land;(c)alistofthenamesandaddresseslastknowntotheconstructingauthorityofallpersonswhototheknowledgeoftheconstructingauthorityareentitledpursuant to
section 18 to claim compensation;(d)astatementastothoseofthepersonsmentionedinparagraph (c) who have not been served
with the noticeof intention to resume and, a further
statement settingout in relation to every such person, the
manner in whichsuch service was attempted and the reasons
for failure toeffect it;(e)a
statement whether or not any person objected in termsof
the notice of intention to resume and, in the case ofsuch
an objection or objections, the name or names ofthe
objector or objectors, a copy of every objection, anda
report by the constructing authority thereon.(4)The
relevant Minister may require any constructing authoritytofurnish,withinatimespecifiedbytherelevantMinister,suchfurtherparticularsandinformationastherelevantMinisterdeems fitwithrespect to an application under thissection.Current as at 1
July 2013Page 15
Acquisition of Land Act 1967Part 2
Taking of land[s 9](5)The
relevant Minister must consider every application madeunder this section, including all statements
and documents, orcopies of documents, accompanying the
application to ensurethat—(a)the
land to be taken may be taken and should be takenfor
the purpose for which it is proposed to be taken; and(b)the constructing authority has taken
reasonable steps tocomply with sections 7 and 8; and(c)if the notice of intention to resume
has not been servedon the owner as defined in section 7(6),
that the failureto do so was due to circumstances beyond the
control ofthe constructing authority.(6)The Governor in Council may, by
gazette notice, declare thatthe land
particularised in the notice is taken for the purposementioned in the notice.(7)Without limiting subsection (6), the
relevant Minister may, bygazette notice, declare that the land
particularised in the noticeis taken for the
purpose mentioned in the notice if—(a)the
objection period for the notice of intention to resumethe
land has ended and no objections were received inresponse to the notice; and(b)ifthelandisbeingtakenforamulti-parcelpurpose—every
other parcel of land required to be takento carry out the
multi-parcel purpose—(i)has been taken
under this Act; or(ii)isthesubjectofaresumptionagreemententeredinto by the
constructing authority; or(iii)is the subject
of a notice of intention to resume forwhichtheobjectionperiodhasendedandnoobjections were received.(8)The taking is effective on the day of
publication of the notice.Page 16Current as at 1
July 2013
Acquisition of Land Act 1967Part 2
Taking of land[s 11]11Amending of gazette resumption notice(1)Section 24AA of theActs
Interpretation Act 1954applies tothe amendment of
a gazette resumption notice.Notes—1ActsInterpretationAct1954,section24AA(Powertomakeinstrument or decision includes power
to amend or appeal)2See section 17 for the power to revoke
a gazette resumption notice.(2)However,totheextentthepowertoamendthegazetteresumption
notice is exercised to correctly describe the landtaken by the notice or to correct another
error, the power is notsubject to sections 7 to 9 or division
3.(3)Also, a gazetting authority may, by
gazette notice, amend agazette resumption notice made by the
Governor in Council tochange the description or area of land
taken under the gazetteresumption notice, but only if—(a)thedescriptionorareawasdescribedinthegazetteresumptionnoticeotherthaninaplanofsurveyregistered in
the land registry; and(b)thedescriptionorareaisdescribedintheamendinggazette notice
in a plan of survey that—(i)complieswiththeSurveyandMappingInfrastructure
Act 2003; and(ii)iscertifiedasaccuratebyacadastralsurveyorwithin the meaning of theSurveyors Act 2003; and(c)thechangeismadesolelytoaccuratelystatethedescription or area of land
taken.(4)However—(a)nopersonshallbeprejudicedinrespectofanymortgage,charge,claim,estate,orinterestexistinginrespect of the land, by reason of the
person having, inconsequenceofthegazetteresumptionnoticeoramendment of the gazette notice, done
or omitted to doanyactorthing,orfailedtoenforceoractuponanyCurrent as at 1 July 2013Page
17
Acquisition of Land Act 1967Part 2
Taking of land[s 12]right,ortocomplywithanyobligationinrespectofsuch
mortgage, charge, claim, estate or interest; and(b)no person shall have any right of
action or claim againstthe constructing authority for
anything bona fide doneunderthegazetteresumptionnoticeoranamendedgazette notice; and(c)nothing in this section contained shall
limit the power ofthe constructing authority to take at any
subsequent timethe whole or any part of the land mentioned
or describedin any gazette resumption notice so amended;
and(d)any amendment of the gazette
resumption notice shallnotprejudiceoraffectthepoweroftheconstructingauthority to
take any land which has been excluded fromthegazetteresumptionnoticebyreasonoftheamendment; and(e)if
the constructing authority again takes land which hasbeenexcludedfromthegazetteresumptionnoticebyreasonoftheamendment,compensationshallnotbepayableinrespectofthevalueofanyworksorimprovements which have been made or
effected on theland by the constructing authority
subsequent to the dateof publication in the gazette of the
gazette resumptionnotice.12Effect of gazette resumption notice(1)Subject to subsection (4), land taken
by a gazette resumptionnotice—(a)shallvest,accordingasthenoticeprescribes,intheCrownorintheconstructingauthoritywhichrequiresthe
land on and from the date of the publication in thegazette of the notice; or(b)if it is taken by the Crown on behalf
of a corporationrepresentingtheCrowninrightoftheStateorconstitutedbyanyActshallvestinthecorporationrequiring the
land if the notice so prescribes and in suchcase,wherethecorporationisnotaconstructingPage 18Current as at 1 July 2013
Acquisition of Land Act 1967Part 2
Taking of land[s 12]authority, the
provisions of section 41 shall apply as ifthe corporation
were a constructing authority.(2A)Where land taken vests in a constructing
authority or, if thegazetteresumptionnoticesoprescribes,inacorporationitshallsovestandbeheldbytheconstructingauthorityorcorporation for the estate or interest
therein of which the landtakenconsistsand,wheretheestateorinterestissuchthatprovisionismadebytheLandTitleAct1994foritsregistration, upon application by the
constructing authority orcorporation and production of agazette copy of the gazetteresumptionnoticeandpaymentoftheprescribedfees,theregistraroftitlesshallregistertheconstructingauthorityorcorporation accordingly.(2B)Where such
application is in respect of the whole estate in feesimple—(a)in
land not under theLand Title Act 1994it shall
containa request for the issue of a certificate of
title for the land;(b)in land under theLand Title Act
1994it may contain arequest for the
issue of a certificate of title for the land;and upon payment
of the prescribed fees the registrar of titlesshallissuetotheconstructingauthorityorcorporationacertificate of title accordingly.(3)Where the land taken is part of land
subject to a building unitsplan registered
under theBuilding Units and Group Titles Act1980theregistraroftitlesshall,uponpaymentoftheprescribedfees,doandexecuteallsuchacts,mattersandthings as the registrar of titles considers
necessary to amendthe building units plan, and may make all
such recordings astheregistraroftitlesconsidersnecessaryintheappropriateregister.(3A)If land taken is
scheme land for a community titles schemeunder theBody
Corporate and Community Management Act1997,
the registrar of titles must, on payment of the prescribedfee,
take the necessary action—(a)toregisteraplanofsurveyidentifyingtheremainingscheme land;
andCurrent as at 1 July 2013Page
19
Acquisition of Land Act 1967Part 2
Taking of land[s 12](b)torecordthetakingofthelandinthefreeholdlandregister; and(c)to
record a new community management statement forthe
scheme.(4)Land granted by the Crown upon trust
for a public purpose, orland comprised in a lease held under
theLand Act 1994, shallupon
and by virtue of the taking thereof become unallocatedState land.(4A)Land
mentioned in subsection (4) may, having regard to thepurpose for which it was taken—(a)bededicated,undertheLandAct1994,asareserveunder the trusteeship of the constructing
authority; or(b)be dedicated, under theLand
Act 1994or this Act, as aroad; or(c)be granted or leased, under theLandAct1994, to theconstructing authority; or(d)be dealt with under another
Act.(4B)Theconstructingauthoritythattakesthelandmentionedinsubsection (4) may also deal with the
land for the purpose forwhich it is taken on and from the day
it is taken, even thoughthe land is yet to be dedicated,
granted, leased or otherwisedealt with under
subsection (4A).(5)Onandfromthedateofthepublicationofthegazetteresumptionnoticethelandtherebytakenshallbevestedorbecome unallocated State land as provided by
the foregoingprovisionsofthissectionabsolutelyfreedanddischargedfromalltrusts,obligations,mortgages,charges,rates,contracts,
claims, estates, or interest of what kind soever, or ifan
easement only is taken, such easement shall be vested intheconstructingauthorityor,wherethegazetteresumptionnotice
prescribes, in the corporation requiring the easement,andtheestateandinterestofeverypersonentitledtothewhole or any part of the land shall
thereby be converted into aright to claim
compensation under this Act and every personwhose estate and
interest in the land is injuriously affected byPage 20Current as at 1 July 2013
Acquisition of Land Act 1967Part 2
Taking of land[s 12]the easement
shall have a right to claim compensation underthis Act.Note—See,
however—(a)theGeothermalEnergyAct2010,sections350Aand350Binrelation to geothermal interests under
that Act; and(b)theGreenhouse Gas
Storage Act 2009, sections 369A and 369B inrelation to GHG interests under that Act;
and(c)theMineral Resources
Act 1989, sections 10AAA and 10AAB inrelation to mining tenement interests under
that Act; and(d)thePetroleum Act
1923, sections 124A and 124B in relation to
1923Act petroleum interests under that Act;
and(e)thePetroleum and Gas
(Production and Safety) Act 2004,sections30AA
and 30AB in relation to petroleum interests under that Act.(5A)Theamountofsuchcompensationmaybeagreeduponbetween the constructing authority and the
claimant subject,however, to the consent of any mortgagee of
the land taken.(5B)Failingsuchagreementeverysuchclaimmaybeenforcedagainst the
constructing authority concerned under, subject toandinaccordancewiththisActandthatconstructingauthority shall
be liable accordingly.(5C)Despitesubsection(5),apersondoesnotobtainarighttoclaim compensation under this Act in
relation to an interest inland that is an interest under a
services contract for the land.(6)Subjecttosection11,publicationofagazetteresumptionnoticeisevidencethatthefollowingprovisionshavebeencomplied
with—(a)forlandtakenunderdivision3inaccordancewitharesumption agreement—that
division;(b)otherwise—sections 7, 8 and 9.(7)Forthwithafterthepublicationofthegazetteresumptionnoticetakinganylandorofagazettenoticeamendingthesame, the constructing authority shall
serve upon every personwhotoitsknowledgeisentitledpursuanttosection18toCurrent as at 1 July 2013Page
21
Acquisition of Land Act 1967Part 2
Taking of land[s 12A]claim
compensation or is a mortgagee of the land a copy ofthe
notice.(8)The omission to serve upon any person
such a copy shall notprejudice or affect in any way the
operation and effect of thenotice in
question.(9)In this section—services
contract, for land, means a contract merely for
theprovision of services on, to, or in relation
to, the land, but doesnotincludeacontractfortheprovisionofservicesunderwhich a person has a right to reside on any
part of the land.Example of a services contract—a contract for the provision of a
cleaning or maintenance service onpremises12AConstructing authority must lodge new
plan of survey forparticular land(1)This
section applies if—(a)land taken under this Act is part
of—(i)landsubjecttoabuildingunitsplanregisteredundertheBuildingUnitsandGroupTitlesAct1980; or(ii)scheme land for
a community titles scheme undertheBody
Corporate and Community ManagementAct 1997;
and(b)the taking of the land affects the
integrity of a boundaryof a lot or common property shown on a
plan registeredundertheBuildingUnitsandGroupTitlesAct1980,Land
Title Act 1994or another Act for the land.(2)The constructing authority for the
acquisition must lodge withthe registrar of
titles a plan of survey showing a new boundaryfor the lot or
common property.Page 22Current as at 1
July 2013
Acquisition of Land Act 1967Part 2
Taking of land[s 12B]12BParticular land may be dedicated as
road(1)ThissectionappliesiflandistakenunderthisActforthepurpose of
roads.(2)The land may be dedicated as a road by
recording a dedicationnotice for the land in the appropriate
register under theLandAct 1994or
theLand Title Act 1994.(3)Iftheregistraroftitlesreceivesadedicationnoticefortheland, the
registrar must register the notice.(4)Theregistrationofthededicationnotice,withoutanythingfurther, opens the road for theLand
Act 1994.(5)In this
section—dedication notice, for land, see
theLand Act 1994, schedule
6.13Provision for
taking particular additional land(1)If—(a)a constructing
authority proposes to take, or has taken,part of any
land; and(b)the taking of the part (theprimary part) will leave,
orhas left, a parcel of land (theadditional land) that
theconstructingauthorityandtheownerofthelandrequired to be taken or that was taken agree
in writing isof no practical use or value to the
owner;the constructing authority also must take
the additional land.(1A)The taking of
the additional land mentioned in subsection (1)is taken to be
for a purpose incidental to the carrying out ofthe purpose for
which the primary part is to be, or was, taken.(2)If,
by reason of the fact that a boundary of land proposed to betaken(theprimaryland)willsevertheprincipalbuildingerectedonthelandfromwhichtheprimarylandwillbesevered and of the circumstances of the case
relevant thereto,it appears to the Governor in Council that
it is desirable thattheconstructingauthorityshouldtakeadditionallandapprovedbytheGovernorinCouncil(alsotheadditionalland)beingthewholeorpartofthelandfromwhichtheCurrent as at 1 July 2013Page
23
Acquisition of Land Act 1967Part 2
Taking of land[s 14]primary land
will be severed the additional land may be takenas
prescribed by this Act and the taking of the additional landshall be deemed to be for a purpose
incidental to the carryingout of the purpose for which the
primary land is taken.(2A)Theconstructingauthoritymaytaketheadditionallandmentioned in subsection (2) when the
constructing authoritytakestheprimarylandoraftertheprimarylandhasbeentaken.(3)Aconstructingauthoritymaysellorotherwisedealwithadditional land
taken by it under this section in such mannerasitthinksfitand
thepower hereby conferred shall not besubject to the provisions of any other Act
which purport torestrict or regulate the exercise by the
constructing authorityofitspowertosellorotherwisedealwithlandortotheprovisions of section 41.14Dealing with title to land affected by
resumption(1)Theregistraroftitlesmay,bynoticeinwriting,requireaperson who has in his or her
possession, custody or controlany instrument
evidencing the title to the land taken by theconstructing
authority named in such notice, to deliver up tothe
land registry, within the time specified in such notice, theinstrument in question.(2)A
person thereunto required by a notice under subsection (1),whofailstodeliveruptothelandregistrytheinstrumentspecified in the
notice within the time therein specified shallbe guilty of an
offence and liable to a penalty of 2 penaltyunits.(2A)Notwithstandingthatsuchpersonhasnotbeenproceededagainstforsuchoffence,unlesssuchfailureisduetocircumstancesbeyondtheperson’scontrol,thepersonshallnotbeentitledtoreceivecompensationortobepaidanyadvanceor,inthecaseofamortgagee,tobemadeanypaymentunderthisActuntiltheinstrumentinquestionisdelivered to the land registry.Page
24Current as at 1 July 2013
Acquisition of Land Act 1967Part 2
Taking of land[s 15](3)The
costs and expenses in connection with the recording orregistration of documents rendered necessary
by the taking ofthe land shall be borne by the constructing
authority.(4)Such costs and expenses may be taxed
by the proper officer ofthe Supreme Court under the rules of
that court.Division 3Taking by
agreementSubdivision 1Resumption
agreements15Meaning ofresumption
agreement(1)Aresumptionagreementisanagreement,complyingwithsubsection (3),
for a constructing authority to take land underthisActentered intobytheauthorityand1ormoreoftheaffected persons
for the land.(2)Anaffectedperson,forlandthesubjectofaresumptionagreement, is
each person who, to the constructing authority’sknowledge—(a)will
be entitled to claim compensation under this Act inrespect of the taking of the land; or(b)is a mortgagee of the land.(3)A resumption agreement must—(a)be written; and(b)be
signed by each affected person who is a party to theagreement; and(c)state—(i)theparticularpurposeforwhichthelandtobetaken is to be taken; and(ii)a description of
the land in the way mentioned insection 7(3)(b);
andCurrent as at 1 July 2013Page
25
Acquisition of Land Act 1967Part 2
Taking of land[s 15A](iii)ifthelandisaneasement—therightsandobligationstobeconferredandimposedbytheeasement.(4)A
resumption agreement may, in relation to the compensationfor
the taking of the land to be taken, for each affected personprovide—(a)for
the compensation to the person; or(b)that
the amount of the compensation is to be fixed underpart
4.(5)Forsubsection(4)(a),thecompensationmayincludethebenefit of an easement or another interest
in land granted bythe constructing authority over any land
under the authority’scontrol.Subdivision
2Process for taking15AApplication of sdiv 2Thissubdivisionappliesifaconstructingauthorityhasentered into a resumption agreement
for particular land.15BLimit on taking under sdiv 2Thelandmaybetakenunderthissubdivisiononlyif,forevery affected
person for the land—(a)the
person—(i)is a party to the resumption
agreement; or(ii)isapartytoanotherresumptionagreementforaparticular
interest in the land; or(iii)has given
written consent to the land being taken inaccordance with
the resumption agreement; or(b)the
person’s interest in the land—(i)has
been taken under this Act; orPage 26Current as at 1 July 2013
Acquisition of Land Act 1967Part 2
Taking of land[s 15C](ii)istakenundersection9immediatelybefore,orwhen, the land is taken under this
subdivision.15CTaking by Governor in Council(1)The constructing authority may apply
to the relevant Ministerfor the land to be taken under this
section.(2)The application must be—(a)madewithin1yearafterthedateoftheresumptionagreement;
and(b)accompanied by—(i)a
copy of the resumption agreement; and(ii)ifthelandisnotidentifiedintheresumptionagreementinthewaymentionedinsection7(3)(b)(i)—a
copy of a plan of survey of the landcertified by a
cadastral surveyor as being accurateor a plan that
is sufficient to substantially identifythe land.(3)TherelevantMinistermay,bywrittennotice,requiretheconstructingauthoritytogivetherelevantMinisterstatedinformationrelatingtotheapplicationwithinastatedreasonable
period.(4)The relevant Minister must consider
the application and anyinformation given under subsection (3)
to ensure the land—(a)may be taken; and(b)should be taken for the purpose for which it
is proposedto be taken.(5)The
Governor in Council may, by gazette notice, declare thatthe
land is taken for the purpose stated in the notice.15DTaking by constructing
authority(1)The constructing authority may, by
gazette notice, declare thatthe land is
taken for the purpose stated in the notice, withoutmaking any application under section
15C.Current as at 1 July 2013Page
27
Acquisition of Land Act 1967Part 2
Taking of land[s 15E](2)However, the constructing authority may take
the land for amulti-parcelpurposeonlyifeveryotherparceloflandrequired to be
taken to carry out the multi-parcel purpose—(a)has
been taken under this Act; or(b)is
the subject of a resumption agreement entered into bythe
constructing authority; or(c)isthesubjectofanoticeofintentiontoresumeforwhich the objection period has ended and no
objectionshave been received.(3)Also, the constructing authority may act
under subsection (1)to take the land only if the authority
is satisfied the land—(a)may be taken;
and(b)should be taken for the purpose for
which it is proposedto be taken.Subdivision
3Miscellaneous15EWhen
taking is effectiveA taking under this division is effective on
the day the gazetteresumption notice is published.15FNon-application of sections 7 to
9Sections 7 to 9 do not apply to the taking
of land under thisdivision.15GWhen
constructing authority is taken to havediscontinued
resumptionIf a constructing authority has not made an
application undersection15Cortakenlandundersection15Dwithin1yearafterthedateofaresumptionagreementtowhichtheauthority is a party—Page 28Current as at 1 July 2013
Acquisition of Land Act 1967Part 3
Discontinuance of taking of land[s 15H](a)theauthorityistakentohavediscontinuedtheresumption of the land the subject of the
agreement; and(b)section 16 applies as if the authority
had served each oftheaffectedpersonsforthelandwithanoticeofintention to resume.15HNo
limit on other acquisition of landThisdivisiondoesnotlimitthepowerofaconstructingauthoritytoacquirelandinanotherway,including,forexample, by purchasing it.Part
3Discontinuance of taking ofland16Discontinuance of
resumption before publication ofgazette
resumption notice(1)Aconstructingauthoritymayatanytimebeforethepublication of the gazette resumption
notice, serve upon everypersonwhohasbeenservedwithanoticeofintentiontoresume a further notice stating that the
constructing authorityis discontinuing the resumption of the
land concerned.(1A)Service of the
further notice shall discontinue the resumptionconcernedandnopersonshallhaveanyclaimforcompensation or other right or remedy
whatsoever against theconstructing authority for any loss or
damage alleged to havebeen occasioned (directly or
indirectly) by the service of thenoticeofintentiontoresumeorthediscontinuanceoftheresumptionexceptaclaimforcompensationforcostsandexpensesincurredbythepersonwhowasservedwiththenotice and any actual damage done to the
land concerned bythe constructing authority.(1B)The constructing
authority and the claimant may agree uponthe amount of
the compensation to be paid under subsectionCurrent as at 1
July 2013Page 29
Acquisition of Land Act 1967Part 3
Discontinuance of taking of land[s 17](1A)
or, upon the reference ofeither of them, such amountmay
be determined by the Land Court.(1C)However, the constructing authority may have
such costs andexpensestaxedbytheproperofficeroftheSupremeCourtundertherulesofthatcourtandthatnopersonshallbeentitled to compensation in excess of
the value of his or herestate or interest in the land.(2)For the purposes of this section,
notwithstanding that noticeunderthissectionhasnotbeenserved,theconstructingauthority shall
be deemed to discontinue a resumption if theapplicationprescribedbysection9(3)hasnotbeenmadewithin the time
prescribed by section 9(4).17Revocation before
determination of compensation(1)If,
at any time after the publication of the gazette resumptionnotice and before the amount of compensation
to be paid inrespect of the taking thereof is determined
by the Land Courtorthepaymentofcompensationinrespectofthetakingissooner made, it is found that the land or
any part thereof is notrequired for the purpose for which it
was taken, the GovernorinCounciloragazettingauthority,bygazettenotice(therevoking gazette
notice), may revoke the gazette resumptionnotice, in whole or in part.(1A)However,therevokinggazettenoticeshallnotbemadeorpublished in the gazette unless the
person entitled as owner tocompensationinrespectofthetakingofthelandhaspreviously agreed in writing to the
revesting as provided bythis section of the land or part to
which that notice relates.(2)Upontherevocationwhollyorotherwisebyarevokinggazette notice
of any gazette resumption notice—(a)thegazetteresumptionnoticeshalltotheextenttowhichsorevokedbedeemedtobeabsolutelyvoidasfrom the making thereof as if it had
not been made; and(b)without prejudice to the provisions of
paragraph (a), theland or part thereof, as the case may be, to
which therevoking gazette notice relates shall revest
in the personPage 30Current as at 1
July 2013
Acquisition of Land Act 1967Part 3
Discontinuance of taking of land[s 17]in
whom the same vested immediately prior to the daywhen
it was taken by the constructing authority underthegazetteresumptionnoticetakingthelandand,subject as hereinafter in this section
provided, shall sorevest for the person’s then estate or
interest therein; and(c)the constructing
authority shall cause a gazette copy ofthe revoking
gazette notice to be lodged with the landregistry, and
the registrar of titles must as soon as maybe thereafter,
at the cost and expense of the constructingauthority,doandexecuteallsuchacts,matters,andthings as the registrar of titles shall
consider necessaryto give effect to this subsection.(2A)Subject to
subsection (2)(a), for subsection (2)(b) the land orpartshallsorevestsubjecttoalltrusts,obligations,mortgages,encumbrances,charges,rates,contracts,claims,estates and interests of what kind soever
subsisting therein orthereover immediately prior to the
taking thereof, but so thatno person shall
be prejudiced by reason of the person having,inconsequenceofthegazetteresumptionnoticetakingtheland
in question and in the meantime, done or omitted to doany
act or thing or failed to exercise any right in respect of
anysuchtrust,obligation,mortgage,encumbrance,charge,rate,contract,claim,estate,orinterestand,withoutlimitingthegenerality of the aforegoing, so that
the time allowed underanysuchtrust,obligation,mortgage,encumbrance,charge,rate, contract, claim, estate, or interest
for the doing of any actortheexercisingofanyrightshallbedeemednottobeshortenedbytheperiodcommencingonandincludingthedateonwhichthelandwastakenandendingwithandincluding the day immediately
preceding the date on whichthe land or part
was revested.(3)Without limiting the generality of the
provisions of subsection(2)(c),theregistraroftitlesmaymakesuchendorsementsuponthedeedofgrantorcertificateoftitleforanylotorparcelofsuchrevestedlandorpart,orissuedsuchnewcertificates of title therefor with
such endorsements thereon (ifany)astheregistraroftitlesmaydeemrequisiteinthecircumstances.Current as at 1
July 2013Page 31
Acquisition of Land Act 1967Part 4
Compensation[s 18](4)Any
person entitled to claim compensation under this Act inrespect of the taking of any land may, upon
the revesting ofsuch land or part thereof pursuant to this
section, claim fromtheconstructingauthoritycompensationforthelossordamage and (if any) costs or expenses
incurred by the personinconsequenceofthetakingofthelandandpriortoitsrevesting.(5)The
constructing authority and the claimant may agree uponthe
amount of the compensation to be paid under subsection(4),
or they may agree that such amount be determined by theLandCourt,inwhichcasesuchamountshall,uponthereference of either of them, be
determined by the Land Courtas if the land
had been taken and not revested and the claimwerelimitedtothecompensationpayableunderthatsubsection.Part 4Compensation18By
whom compensation may be claimed(1)Subjecttosubsections(2),(3),(4A)and(5)compensationwhereto a right
is had under section 12 may be claimed fromthe constructing
authority under, subject to and in accordancewith the
provisions of this part.(2)In the case of
the inability or incapacity of any person entitledtoclaim,theclaimmaybe
madebytheperson’sguardian,trusteeorcommitteeor,ifthereisnoguardian,trusteeorcommittee, the Public Trustee of
Queensland.(3)Compensationshallnotbeclaimablebyorpayabletoaperson who is
lessee, tenant or licensee of any land taken ifthe constructing
authority upon written application allows theperson’s estate
or interest to continue uninterrupted.(3A)Ifaperson’sinvestmentpropertyistakenunderthisAct,compensationforcostsmentionedinthedefinitioncostsattributabletodisturbance,paragraphs(a)and(b),underPage
32Current as at 1 July 2013
Acquisition of Land Act 1967Part 4
Compensation[s 18]section 20(5) is
claimable by, and payable to, the person forthe purchase of
land by the person to replace the investmentproperty.(4)Subsection(4A)appliestolandundertheLandTitleAct1994.(4A)Where,inrespectofanestateorinterestinthelandtakenwhich is not duly registered or notified in
the land registry, aclaimant makes a claim for
compensation subsequent to thepayment to
another claimant of compensation in respect of agreater estate or interest in the land taken
which included theunregisteredorunnotifiedestateorinterestpursuanttoaclaim made by
such other claimant in or in connection withwhich the first
mentioned claimant did not disclose in writingsuch
unregistered or unnotified estate or interest, the claimantfirst mentioned in this subsection shall not
be entitled to anycompensation whatever from the constructing
authority.(5)The claim for compensation of a
trustee or trustees of any landin respect of
the taking thereof shall be limited to the amountof
actual damage caused to the trust by reason of the taking,andnosuchtrusteeshallhaveanyotherright,remedy,orclaim whatsoever in respect of such taking
against the Crownor any other person whomsoever and this Act
and every otherrelevantActorlaworrule,practice,orprocessoflaw,orjudgment of any court of competent
jurisdiction, shall be read,construed and
applied subject to this subsection.(6)ForthepurposesofaclaimforcompensationinrespectofcommonpropertyunderandwithinthemeaningoftheBuilding Units and Group Titles Act
1980, the body corporateconstitutedunderthatActbytheproprietorswithinthemeaning thereof of the units comprised
in the building unitsplanconcernedshallbedeemedtobetheownerofsuchcommon
property.(7)Except by unanimous resolution of all
proprietors such bodycorporate shall not agree upon the
amount of compensation.(8)Unlessotherwiseagreedbyunanimousresolutionofallproprietors, the amount of
compensation shall be distributedCurrent as at 1
July 2013Page 33
Acquisition of Land Act 1967Part 4
Compensation[s 18]amongtheproprietorsinsharesproportionaltotheunitentitlements of
their respective units.(9)Foraclaimforcompensationforcommonpropertyforacommunity titles
scheme, the body corporate for the schemeis taken to be
the owner of the common property.(10)However—(a)thebodycorporatemayagreeontheamountofcompensation only by resolution without
dissent; and(b)unless the body corporate agrees by
resolution withoutdissent to a different distribution of the
compensation, itmust be distributed among the owners of lots
in sharesproportionatetotherespectiveinterestschedulelotentitlements of their lots.(11)Insubsections(9)and(10),thefollowingwordshavethemeaningsgivenbytheBodyCorporateandCommunityManagement Act
1997—•body
corporate•common property•community titles scheme•interest schedule lot entitlement•lot•owner•resolution without dissent.(12)Subsection (13)
applies to the proprietor of a lot in a buildingunitsplanundertheBuildingUnitsandGroupTitlesAct1980, or the owner
of a lot in a community titles scheme undertheBody
Corporate and Community Management Act 1997,inrelationtowhichaclaimforcompensationforcommonproperty
mentioned in subsection (6) or (9) is made.(13)The
making of the claim for compensation for the commonproperty does not stop the proprietor or
owner making a claimforcompensationfordamagesufferedbytheproprietororPage
34Current as at 1 July 2013
Acquisition of Land Act 1967Part 4
Compensation[s 19]owner as a
result of the taking of the common property andthe effect of
the taking on the proprietor’s or owner’s lot.(14)In
subsection (3A)—investment property, of a person,
means any land held by theperson for investment purposes.19Claim for compensation(1)A claim for compensation shall be in
writing, shall be servedupontheconstructingauthority,shallstateinfullthenameand address of
the claimant, shall be signed by the claimant,andshallcontainorbeaccompaniedbyeachofthefollowing—(a)adescriptionofthelandtakenandastatementofthearea
thereof;(b)astatementofthenatureandparticularsoftheclaimant’s estate or interest in the
land taken;(c)astatement(which, inthecaseoftheowner,shallbeverifiedbystatutorydeclaration)astowhetherornottheclaimant’sestateorinterestinthelandtakenissubjecttoanytrust,obligation,mortgage,lease,agreement to
lease, charge, rate, contract, claim or otherestate or
interest whatsoever and, if so, the nature andparticulars of
those of the aforesaid to which the estateor interest is
subject;(d)an itemised statement of the claim,
showing the natureand particulars of each item and the amount
claimed inrespect thereof;(e)the
total amount of compensation claimed.(2)Where the estate or interest of the claimant
is not registered ornotified in the land registry, the
claim shall be accompaniedby proof of title to the estate or
interest claimed, which proofshall include
copies of or abstracts from all documents (if any)necessary to establish in law the estate or
interest.Current as at 1 July 2013Page
35
Acquisition of Land Act 1967Part 4
Compensation[s 20](3)A
claim for compensation may be served on the constructingauthority only within 3 years after the day
the land was taken.(4)Despite subsection (3), the
constructing authority may accept,anddealwith,aclaimforcompensationservedbytheclaimant more
than 3 years after the day the land was taken ifthe
constructing authority is satisfied it is reasonable in all
thecircumstances to do so.(5)If
the constructing authority does not accept a claim served bytheclaimantmorethan3yearsafterthedaythelandwastaken,theclaimantmayapplytotheLandCourttodecidewhetheritisreasonableinallthecircumstancesfortheconstructing authority to accept the
claim.(6)IftheLandCourtdecidesitisreasonableinallthecircumstancesfortheconstructingauthoritytoaccepttheclaim, the constructing authority must
accept, and deal with,the claim under this Act.(7)If the constructing authority accepts
and deals with a claim forcompensation served by the claimant
more than 3 years afterthedaythelandwastaken,theLandCourtmusttakeintoaccount the late
service of the claim in deciding any amountof interest
payable under section 28 in relation to the claim.20Assessment of compensation(1)In assessing the compensation to be
paid, regard shall in everycase be had not
only to the value of land taken but also—(a)to
the damage, if any, caused by any of the following—(i)the severing of the land taken from
other land ofthe claimant;(ii)theexerciseofanystatutorypowersbytheconstructingauthorityotherwiseinjuriouslyaffectingtheclaimant’sotherlandmentionedinsubparagraph (i); and(b)to the claimant’s costs attributable
to disturbance.Note—Page 36Current as at 1 July 2013
Acquisition of Land Act 1967Part 4
Compensation[s 20]See,
however—(a)theGeothermalEnergyAct2010,section350Dinrelationtogeothermal interests under that Act;
and(b)theGreenhouse Gas
Storage Act 2009, section 369D in relation toGHG
interests under that Act; and(c)theMineralResourcesAct1989,section10AADinrelationtomining tenement interests under that Act;
and(d)thePetroleumAct1923,section124Cinrelationto1923Actpetroleum
interests under that Act; and(e)thePetroleum and Gas (Production and
Safety) Act 2004,section30AD in relation
to petroleum interests under that Act.(2)Compensation shall be assessed according to
the value of theestate or interest of the claimant in the
land taken on the datewhen it was taken.(2A)However, in assessing the compensation, a
contract, licence,agreementorotherarrangement(arelevantinstrument)entered into in relation to the land after
the notice of intentionto resume was served on the claimant
must not be taken intoconsideration if the relevant
instrument was entered into forthesoleordominantpurposeofenablingtheclaimantoranother person to obtain compensation for an
interest in theland created under the instrument.(3)In assessing the compensation to be
paid, there shall be takenintoconsideration,bywayofset-offorabatement,anyenhancement of the value of the interest of
the claimant in anylandadjoiningthelandtakenorseveredtherefrombythecarryingoutoftheworksorpurposeforwhichthelandistaken.(4)But
in no case shall subsection (3) operate so as to require anypayment to be made by the claimant in
consideration of suchenhancement of value.(5)In this section—costs
attributable to disturbance, in relation to
the taking ofland, means all or any of the
following—(a)legalcostsandvaluationorotherprofessionalfeesreasonablyincurredbytheclaimantinrelationtotheCurrent as at 1 July 2013Page
37
Acquisition of Land Act 1967Part 4
Compensation[s 20]Page 38preparationandfilingoftheclaimant’sclaimforcompensation;(b)the
following costs relating to the purchase of land by aclaimant to replace the land taken—(i)stampdutyreasonablyincurredorthatmightreasonablybeincurredbytheclaimant,butnotmore than the amount of stamp duty
that would beincurredforthepurchaseoflandofequivalentvalue to the
land taken;(ii)financialcostsreasonablyincurredorthatmightreasonably be incurred by the claimant in
relationto the discharge of a mortgage and the
execution ofa new mortgage, but not more than the amount
thatwould be incurred if the new mortgage
secured therepayment of the balance owing in relation
to thedischarged mortgage;(iii)legal costs reasonably incurred by the
claimant;(iv)otherfinancialcosts,otherthananytaxationliability,
reasonably incurred by the claimant;(c)removalandstoragecostsreasonablyincurredbytheclaimant in
relocating from the land taken;(d)costs reasonably incurred by the claimant to
connect toanyservicesorutilitiesonrelocatingfromthelandtaken;(e)other financial costs that are
reasonably incurred or thatmight reasonably
be incurred by the claimant, relating totheuseofthelandtaken,asadirectandnaturalconsequence of
the taking of the land;(f)anamountreasonablyattributedtothelossofprofitsresultingfrominterruptiontotheclaimant’sbusinessthat
is a direct and natural consequence of the taking ofthe
land;(g)other economic losses and costs
reasonably incurred bythe claimant that are a direct and
natural consequence ofthe taking of the land.Current as at 1 July 2013
Acquisition of Land Act 1967Part 4
Compensation[s 21]Example of costs
for paragraph (g)—cost of school uniforms for children
enrolled in a new schoolbecause of relocation from the land
taken21Grant of easement etc. or transfer of
land in satisfactionof compensation(1)Theconstructingauthorityandtheclaimantmayagreethattheconstructingauthoritywillgranttheclaimant,insatisfactionwhollyorpartlyoftheclaimant’sclaimforcompensation, any easement, right of
way, lease or other rightof occupation, or any other right,
privilege or concession in,upon,overorunderthelandtakenoranyotherlandtheproperty of the constructing
authority.(1A)Also, the
constructing authority and the claimant may agreethat
the constructing authority will transfer land held in feesimplebytheconstructingauthoritytotheclaimantinsatisfactionwhollyorpartlyoftheclaimant’sclaimforcompensation.(2)In
such cases the parties may agree that the extent to whichthe
grant or transfer shall satisfy the claim for compensationshall be determined by the Land Court, and
the jurisdiction ofthe Land Court to determine the compensation
shall includejurisdiction to determine the extent of such
satisfaction.22Crown grant in satisfaction of
compensation(1)WheretheCrownistheconstructingauthority,andtheclaimantagrees,theGovernorinCouncilmaygrantinfeesimpleordemiseforanylesserestateorinteresttotheclaimant,insatisfactionwhollyorpartlyoftheclaimforcompensation, any unallocated State
land.(2)For the purposes of subsection (1),
the relevant Minister, otherthan the State
Development Minister, may close a road thattraversesoradjoinslandownedbytheclaimant,andtheGovernorinCouncilmaygrantthelandintheroadtotheclaimant.Current as at 1
July 2013Page 39
Acquisition of Land Act 1967Part 4
Compensation[s 23]23Advance against compensation(1)A claimant for compensation may at any
time after the date onwhich the claimant delivered to the
constructing authority hisorherclaimforcompensationinaccordancewiththerequirements of section 19, apply to
the constructing authorityto make to the claimant an advance not
exceeding the amountprescribed by subsection (3) in
respect of the compensationclaimable by the
claimant.(2)Subject to being satisfied that the
applicant is entitled to claimcompensation and
to subsection (3) the constructing authorityshallmaketotheapplicanttheadvanceappliedforbytheapplicantinrespectofthecompensationclaimedbytheapplicant.(3)Theamountofanadvanceunderthissectionshallnotexceed—(a)wheretheconstructingauthorityhasmadetotheclaimantanofferinwritingofanamountofcompensationinsettlementoftheclaimant’sclaim—that
amount; or(b)where the constructing authority has
not made the offermentionedinparagraph(a)—anamountequaltoitsestimate of the
amount of compensation payable to theclaimant.(4)Subject to subsections (5) and (6),
any amount payable to aclaimant under this section which is
not paid within 90 daysafter the claimant applied for the
payment shall be recoverableby the claimant
as a debt due and unpaid to the claimant bythe constructing
authority.(5)Beforepayingtheadvancetheconstructingauthoritymayrequiretheclaimanttosatisfyitregardingtaxes,ratesandother moneys which, if unpaid, would be a
charge upon theland,andmayreducetheadvancebyanysumwhich,inrespect of any thereof, is unpaid or,
as respects any period oftime prior to the date when the land
was taken, will becomepayable.Page 40Current as at 1 July 2013
Acquisition of Land Act 1967Part 4
Compensation[s 24](6)Where the land concerned is subject to a
mortgage at the datewhenitistakentheconstructingauthoritymayreducetheadvance by the sum due to the
mortgagee.(7)TheconstructingauthoritymaypaytotheCrownortothelocal government
concerned or to the mortgagee any sum bywhich the
advance has been reduced under subsection (5) or(6).24Reference of
claim for compensation to Land Court(1)Subject to this section either the
constructing authority or theclaimantmayrefertotheLandCourtforhearinganddetermination the matter of the amount of
the compensation.(2)If the amount of the compensation has
not been sooner agreedupon, the claimant may so refer that
matter at any time afterthe date upon which the claimant
delivered to the constructingauthorityaclaimforcompensationinaccordancewiththerequirements of section 19.(2A)The claimant
shall make the reference by filing in the office ofthe
registrar of the Land Court copies of the claim deliveredby
the claimant to the constructing authority and of the noticeofintentiontoresumeandagazettecopyofthegazetteresumption notice taking the land.(3)The claimant shall not amend the claim
filed by the claimantin the office of the registrar of the
Land Court except uponleave granted by that court (which
leave the court may grantupon such terms as it deems just,
including terms with respectto the payment
of costs).(4)Upon the application of the
constructing authority, the LandCourtmayordertheclaimanttofileintheofficeoftheregistrar of the Land Court such
further or other particularswith respect to
the claim for compensation as, having regardto the
provisions of section 19, the court deems fit.(4A)A
claimant who fails to comply with such an order within thetime
specified therein shall be deemed not to have referred tothe
Land Court the claim in question.Current as at 1
July 2013Page 41
Acquisition of Land Act 1967Part 4
Compensation[s 25](5)If
the amount of the compensation has not been sooner agreedupon
and—(a)if the claimant has not sooner
delivered to it a claim forcompensationsubstantiallyinaccordancewiththerequirementsofsection19,theconstructingauthoritymay
so refer the matter at any time after the expirationof
the period of 3 months next following the date of thegazette containing the gazette resumption
notice takingthe land; or(b)iftheclaimanthasdeliveredtotheconstructingauthorityaclaimforcompensation,theconstructingauthority may so
refer that matter at any time after theexpiration of
the period of 3 months next following thedateofthegazettecontainingthegazetteresumptionnoticetakingtheland,unlessthereferencehasbeensooner made by
the claimant.(6)Theconstructingauthorityshallmakethereferenceinthemannerprescribedbysubsection(2A)savethatiftheclaimanthasnotdeliveredtotheconstructingauthorityaclaimforcompensationsubstantiallyinaccordancewithsection19,theninthesteadofacopyoftheclaimtheconstructingauthorityshallfileadocumentcontainingoraccompanied by all of the particulars
required to be containedin or to accompany the claim so far as
those particulars areknown to it but, in relation to
paragraphs (d) and (e), statingamounts which it
is willing to pay.25Reference to Land Court by
constructing authority(1)Wheretheconstructingauthoritymakesareferencementioned in
section 24, the Land Court upon application inthat behalf made
by the constructing authority, shall order thatthe claimant may
enter an appearance on the reference on orbefore the date
fixed by the order.(2)A claimant may appear on the reference
by filing in the officeof the registrar of the Land Court, on
or before the date fixedby the order, a claim for compensation
in accordance with therequirements of section 19, and
thereupon section 24(3) andPage 42Current as at 1
July 2013
Acquisition of Land Act 1967Part 4
Compensation[s 26](4) shall apply
and the matter of the amount of compensationshallbeheardanddeterminedasifthereferencehadbeenmade in the
first instance by the claimant.(2A)However, an order as provided for by section
24(4) may bemade in respect of such appearance and, if
the claimant failsto comply with such order within the time
therein specified,theclaimantshallbedeemedtohavefailedtoenteranappearance on the reference.(3)A claimant who fails to enter an
appearance on a referencemadebytheconstructingauthorityshallnotbeentitledtoappear or to be heard by the Land Court upon
the hearing ofthereferencesavebyleaveofsuchcourt(whichleavethecourt may grant upon such terms as it
deems just, includingterms with respect to the payment of
costs).(4)In the case of a reference made by the
constructing authority,theLandCourtmayhearanddeterminethematteroftheamount of compensation in the absence
of the claimant wherethe claimant fails to enter an
appearance on or before the datefixedbyorderofthecourtorwhere,havingsoenteredanappearanceorhavingleavetoappear,theclaimantfailstoappear at the hearing.(5)Where the reference has been made by
the claimant in the firstinstance, the Land Court may hear and
determine the matterof compensation in the absence of the
claimant if the claimantfails to appear at the hearing.26Jurisdiction relating to
compensation(1)TheLandCourthasjurisdictiontohearanddetermineallmatters relating to compensation under this
Act.(3)Thedecision(whetheroftheLandCourtconstitutedbyasingle member or, as the case may be,
the Land Appeal Court)shall be in writing and the registrar
of the Land Court shalltransmitthe
decisiontothe registraroftheSupremeCourt,who
shall cause the same to be filed in the registry of the
lattercourt.(4)The
decision—Current as at 1 July 2013Page
43
Acquisition of Land Act 1967Part 4
Compensation[s 26A](a)shallbefinalasregardstheamountofcompensationawarded;
and(b)unless the amount shall have been paid
into the SupremeCourtpursuanttosection29,shallbefinalforallpurposesandhavetheeffectofajudgmentoftheSupreme Court and may be enforced
accordingly.(5)Where, pursuant to section 29, the
amount of compensationawarded is paid into the Supreme Court
the decision shall notbe final as regards the right or title
of the claimant or any otherpersonwhomsoevertobepaidthatamountoranypartthereof.26AJurisdiction about recovery of advance
againstcompensation(1)This
section applies if, in relation to land taken—(a)aconstructingauthorityadvancesanamounttoaclaimant under section 23; and(b)the Land Court later decides an amount
of compensationpayabletotheclaimantthatislessthantheamountmentioned in
paragraph (a).(2)The amount (theoutstanding
amount) that is the differencebetweenthefollowingamountsisanamountowingtotheconstructing authority by the
claimant—(a)the amount mentioned in subsection
(1)(a);(b)the total of the amount of
compensation decided by theLand Court and
any interest payable on that amount tothe
claimant.(3)TheLandCourthasjurisdictiontomakeanorderthattheoutstandingamountbepaidbytheclaimanttotheconstructing authority.(4)The Land Court may make an order under
subsection (3) atany time after it decides the amount of
compensation.(5)The Land Court may order the claimant
to pay interest on theoutstanding amount for all or any part
of the period—Page 44Current as at 1
July 2013
Acquisition of Land Act 1967Part 4
Compensation[s 27](a)starting on the day the amount mentioned in
subsection(1)(a) was advanced to the claimant;
and(b)ending at the beginning of the day the
claimant pays theoutstanding amount to the constructing
authority.(6)Interestmentionedinsubsection(5)ispayablebytheclaimant—(a)attheratestatedintheorderthattheLandCourtconsiders appropriate; and(b)when the outstanding amount is
payable.(7)An order under subsection (3) may be
enforced as if it were anorder made by the Supreme
Court.27Costs(1)Subjecttothissection,thecostsofandincidentaltothehearing and determination by the Land
Court of a claim forcompensation under this Act shall be
in the discretion of thatcourt.(2)If
the amount of compensation as determined is the amountfinally claimed by the claimant in the
proceedings or is nearerto that amount than to the amount of
the valuation finally putin evidence by the constructing
authority, costs (if any) shallbe awarded to
the claimant, otherwise costs (if any) shall beawarded to the
constructing authority.(3)Subsection (2)
does not apply to any appeal in respect of thedecision of the
Land Court or to costs awarded pursuant tosection 24(3) or
section 25(3).28Interest(1)Subject to subsection (2), in respect of the
period or any partof the period commenced on and including the
date on andfrom which any land is taken and ending on
and including thedayimmediatelyprecedingthedateonwhichpaymentofcompensationismadetheLandCourtor,uponappeal,theCurrent as at 1 July 2013Page
45
Acquisition of Land Act 1967Part 4
Compensation[s 29]Land Appeal
Court may order that interest be paid upon theamount of
compensation determined by it.(1A)Such
interest shall be at such rate per centum per annum as theLand
Court or, upon appeal, the Land Appeal Court, deemingreasonable, fixes by the order.(1B)Interest so
ordered to be paid shall be payable as if it were partofthecompensationinquestionandshallbeaddedtotheamount thereof and be payable by the
constructing authorityaccordingly.(2)Interestshallnotbepayableinrespectofanyamountofcompensation advanced under section
23.29Where right to compensation is
questioned(1)Where the title by reason whereof
compensation is claimedunder this Act comes in
question—(a)intheLandCourtor,uponappeal,theLandAppealCourt during the hearing and determination
of the claimfor compensation; or(b)during negotiations between the constructing
authorityand the claimant;nevertheless the
said court shall have power to determine or,asthecasemaybe,theconstructingauthorityandtheclaimant may
agree upon the amount of the compensation tobe paid.(1A)In such case the
constructing authority shall pay the amount ofcompensationdeterminedoragreeduponintotheSupremeCourt.(2)Where subsequent to the date when
compensation has beendeterminedoragreedupon,butbeforetheconstructingauthority has
paid the compensation to the claimant, the titleby
reason whereof the compensation was claimed under thisAct
comes in question to the knowledge of the constructingauthority, it shall pay the amount of the
compensation into theSupreme Court.Page 46Current as at 1 July 2013
Acquisition of Land Act 1967Part 4
Compensation[s 30](3)A
constructing authority may pay into the Supreme Court theamount of any compensation under this Act
where—(a)thepersontowhomtheamountispayablefailsorrefuses to accept payment thereof;
or(b)theconstructingauthorityisunableforanyreasonwhatsoevertomaketotheclaimantpaymentoftheamountortoobtainfromtheclaimantagoodandsufficient discharge for such
payment.(4)ThepaymentpursuanttoaprovisionofthissectionofanyamountofcompensationintotheSupremeCourtshalldischarge in
full the liability of the constructing authority topay
that amount pursuant to the determination or agreementby
virtue whereof it became payable.(5)Upon
application in that behalf the Supreme Court or a judgethereofmayorderthatanymoneypaidintothatcourtpursuant to a
provision of this section or part thereof shall bepaid
to or applied for the benefit of such person as the saidcourt or judge finds to be entitled
thereto.(6)The said court or judge may subject
such order to such termsand conditions as the court or judge
deems just and may, atthecourt’sorjudge’sdiscretion,orderanypartytotheapplication to pay to any other party
thereto such costs as thecourt or judge deems just.30Limited interests(1)Where compensation is determined or agreed
to be paid to anyclaimant in respect of a partial or
qualified interest held by theclaimant in the
land taken and such person is not entitled tosell or dispose
of such interest—(a)theconstructingauthorityshallpaytheamountofthecompensation into the Supreme Court;
and(b)the Supreme Court or a judge may upon
application inthatbehalforderthattheamountonanypartthereofshallbeappliedtoany1ormoreofthefollowingpurposes, that
is to say—Current as at 1 July 2013Page
47
Acquisition of Land Act 1967Part 4
Compensation[s 31](i)the
discharge of any debt or encumbrance affectingthe land, or
affecting any land settled therewith, orto the same or
like uses, trusts, or purposes;(ii)the
purchase of other land to be conveyed, limited,andsettleduponorforthelikeuses,trusts,orpurposes;(iii)removing or replacing any buildings on the
land, orsubstituting others in their stead;(iv)thepurchaseofsuchsecuritiesastheSupremeCourt or judge
may direct, to be settled in the samemanner as the
land;(v)inpaymenttoanypartiesbecomingabsolutelyentitledthereto,or,incaseoftheirdisabilityorincapacity,totheirrespectiveguardians,trustees,or
committees (or if there is no guardian, trustee orcommittee, to the Public Trustee of
Queensland),as the case may be.(2)ThecostsofandincidentaltoanyapplicationunderthissectionshallbeinthediscretionoftheSupremeCourtorjudge.(3)Nothing in this section shall be deemed to
prevent any personwho has a partial or other qualified
interest in land to whichinterestthepersonissolelyentitled,andwhichthepersonmayabsolutelysellordisposeof,fromreceivinganycompensationawardedtothepersoninrespectofsuchinterest, or
which has been agreed to be paid to the person.31Powers of Supreme Court in respect of
building unitsWherethewholeofthelandcomprisedinabuildingunitsplan registered
under theBuilding Units and Group Titles Act1980,istakenunderthisAct,theSupremeCourtofQueenslandshallhaveandmayexerciseinrelationtothebuilding shown in such building units
plan such jurisdictionunder that Act as it would have were
such building destroyedfor the purpose of that Act on and by
such taking.Page 48Current as at 1
July 2013
Acquisition of Land Act 1967Part 4
Compensation[s 31A]31APowers of District Court for community
titles scheme(1)This section applies if—(a)thewholeoftheschemelandforacommunitytitlesschemeundertheBodyCorporateandCommunityManagement Act
1997is taken under this Act; and(b)the scheme land includes at least 1
lot that is, under theLand Title Act 1994—(i)a lot on a
building format plan of subdivision; or(ii)a
lot on a volumetric format plan of subdivision,and wholly
contained within a building.(2)The
District Court may exercise, in relation to any buildingforming part of the scheme land, the
jurisdiction it would haveunder theBody Corporate
and Community Management Act1997on
the destruction of the building.32Mortgages(1)Where the land taken is subject to a
mortgage at the date whenit is taken, upon application by the
mortgagee—(a)the Land Court or, upon appeal, the
Land Appeal Courtshall order that payment be made to the
mortgagee of; or(b)ifthecompensationisagreedupon,theconstructingauthority shall
pay to the mortgagee;somuchoftheamountofthecompensationasdoesnotexceed the sum due to the mortgagee.(2)Paymentshallnotbemadetoamortgageeunderthissection—(a)inprioritytoanyotherclaimant,savethemortgagor,unless the
mortgagee would, if the land had been sold onthe date when it
was taken, have been entitled to suchpriority;
or(b)in priority to any taxes, rates or
other moneys chargedupon the land taken in favour of the
Crown or any localgovernment.Current as at 1
July 2013Page 49
Acquisition of Land Act 1967Part 4
Compensation[s 33](3)For
the purposes of this section the sum due to the mortgageeincludes interest payable under the mortgage
up to the date ofpaymentorthelastdayofanyperiodinrespectwhereofinterest upon the amount of compensation has
been ordered tobe paid pursuant to section 28, whichever is
the earlier.33Rent-charge or annuity(1)If the land in respect of which
compensation is determined orhasbeenagreedtobepaidissubjecttoarent-chargeorannuity,theLandCourtor,uponappeal,theLandAppealCourt shall, upon application by the person
entitled to suchrent-chargeorannuity,determinewhatpartofsuchcompensationshallbepaidtothepersonsoentitledinredemption thereof.(2)If
the land is part of land subject to a rent-charge or
annuity,the Land Court or, upon appeal, the Land
Appeal Court uponthelikeapplicationshalldeterminewhatpartofsuchrent-chargeorannuityshallberedeemed,andwhatpartofsuch compensation shall be paid in the
redemption thereof, sothat the remaining part of the land
subject to the rent-charge orannuity shall be
as good security as theretofore for the partthereof
remaining unredeemed.34Where part only
of land subject to rent is takenIf the land in
respect of which compensation is determined orhas been agreed
to be paid is part of land in respect of whichany rent is
payable, the Land Court or, upon appeal, the LandAppeal Court shall, upon application by the
person liable topay rent, determine what part of such rent
shall cease to bepayable, so that the rent ceasing to be
payable shall bear thesame proportion to the whole rent as
the value of the land inrespect of which compensation is
determined or agreed to bepaid bears to the value of the whole
of the land.Page 50Current as at 1
July 2013
Acquisition of Land Act 1967Part 5
General[s 35]35Taxes, rates and chargesAny amount due
and unpaid as at the date of the taking of theland of any
taxes, rates or other moneys charged upon the landtaken in favour of the Crown or any local
government shall bea charge upon the compensation payable under
this Act to aclaimantwhoislegallyliableforpaymentthereof,andtheconstructingauthoritymaydeductfromsuchcompensationand pay to the
Crown or local government concerned any suchamount.Part
5General36Powers of entry etc.(1)For
the purposes of this Act any member, officer, employee,contractor or agent of the constructing
authority or any personauthorisedbyitinthatbehalfmayexerciseanyofthefollowing
powers—(a)enteruponanyland,forthepurposeofmakinganyinspection, valuation, survey or taking
levels;(b)affix or set up thereon
trigonometrical stations, surveypegs,marks,orpoles,andfromtimetotimealter,remove, inspect, reinstate and repair the
same;(c)dig and bore into the land so as to
ascertain the nature ofthe soil, and set out the lines of any
works thereon;(d)do all things necessary for the
purposes aforesaid.(2)The power to enter upon any land
includes power to—(a)re-enter from time to time; and(b)remain upon that land for such time as
is necessary toachieve the purpose of the entry; and(c)takesuchassistants,vehicles,materials,equipmentorthingsasarenecessarytoachievethepurposeoftheentry.Current as at 1
July 2013Page 51
Acquisition of Land Act 1967Part 5
General[s 36A](3)When
practicable, not less than 7 days notice in writing shallbe
given to the occupier or, if there is no occupier, the ownerof
the land of the intention to enter thereon, and the
authorityunder which the person entering claims to
enter or has enteredshall, if required by such owner or
occupier, be produced andshown.(4)Every person who—(a)without due authority, destroys, mutilates,
defaces, takesaway,oraltersthepositionofanytrigonometricalstation, survey
peg, mark, or pole fixed or set up by anyperson under the
authority of this section; or(b)wilfullyobstructsorattemptstoobstructanypersonacting under the
authority of this section;shall be guilty of an offence against
this Act and liable to apenalty not exceeding 4 penalty
units.(5)Theconstructingauthorityshallbeliableforcompensationfor the actual
damage (if any), done to the land by reason ofthe exercise of
any power conferred by this section.(6)Subsection (5) applies subject to section
37(4).(7)Compensation pursuant to subsection
(5) may be claimed andagreed upon or determined as
prescribed by section 37(3) and(5).36AMinister may act for Crown as
constructing authorityTheMinisterisauthorisedandrequiredtoexercisesuchpowers,performsuchfunctionsandtakesuchstepsasarepermittedorrequiredbythisActforthepurposeoftakingland on behalf
of the Crown as a constructing authority.36BDelegation by Minister(1)The
Minister may delegate the Minister’s functions under thisAct
to an appropriately qualified officer or employee of thedepartment.Page 52Current as at 1 July 2013
Acquisition of Land Act 1967Part 5
General[s 37](2)However,theMinistercannotdelegatetheMinister’sfunctions under
section 9 in relation to an application for thetaking of land
if an objection was received in response to anotice of
intention to resume for the land.(3)A
delegation of a function may permit the subdelegation ofthe
function to an appropriately qualified officer or employeeof
the department.(4)In this section—appropriatelyqualified,forafunction,meanshavingthequalifications, experience or standing to
perform the function.Example of standing for an officer of
a department—the officer’s classification or level
in the departmentdepartment,foradelegationoftheMinister’sfunctions,means the
department administered by the Minister.functionsincludes powers.MinisterincludesarelevantMinister,otherthantheStateDevelopment
Minister.37Temporary occupation of land(1)The constructing authority may
temporarily occupy and useanylandforthepurposeofconstructing,maintainingorrepairing any works, and may exercise any of
the followingpowers—(a)take
therefrom stone, gravel, earth, and other material;(b)deposit thereon any material;(c)form and use temporary roads
thereon;(d)manufacture bricks or other materials
thereon;(e)erectworkshops,sheds,andotherbuildingsofatemporary nature
thereon.(2)The constructing authority or the
person having the charge ofthe works shall,
before occupying or using any land as hereinprovided,andexceptinthecaseofaccidentrequiringCurrent as at 1 July 2013Page
53
Acquisition of Land Act 1967Part 5
General[s 38]immediaterepair,givetotheoccupieror,ifthereisnooccupier,theownerthereofnotlessthan7daysnoticeinwriting, and shall state in such
notice the use proposed to bemadeofthelandandanapproximateperiodduringwhichsuch
use is expected to continue.(3)The
owner of the land or any other person having any estate orinterest in the land may, at any time during
such occupation orwithin3monthsthereafter,givenoticeinwritingtotheconstructingauthoritythattheownerclaimscompensation,and, subject to
giving such notice, if the land is not taken theowner and all such other persons may recover
under this Actcompensation for all damage done, but not in
the case of theowner or any such other person exceeding the
compensationwhich would have been payable to him or her
had the landbeen taken.(4)No
compensation shall be payable for any act or thing doneunder this section, the right or authority
to exercise which isreserved by any Act, or by any
regulation, Crown grant, orotherinstrument,excepttotheextentthereinmentioned,notwithstandingthatthetermsandconditionsimposedbysuchAct,regulation,grant,orinstrumenthavenotbeenperformed.(5)The
constructing authority and the claimant may agree uponthe
amount of compensation to be paid under this section orthey
may agree that such amount be determined by the LandCourt, in which case such amount shall, upon
the reference ofeither of them, be determined by the Land
Court as if the landhadbeentakenandtheclaimwerelimitedtothecompensation recoverable under this
section.38Refusal to give up land(1)If the owner or occupier of any land
taken or occupied underthis Act, or any other person, refuses
to give up possessionthereof, or obstructs the constructing
authority or any personappointedinwritingbyit,theconstructingauthoritymayissueitswarranttothesherifftodeliverpossessionofthesametothepersonappointedinthewarranttoreceivePage 54Current as at 1 July 2013
Acquisition of Land Act 1967Part 5
General[s 39]possession,andonreceiptofthewarrantthesheriffshalldeliver possession of such land
accordingly.(2)Thecostsoftheissueandexecutionofthewarrant,tobesettled by the sheriff, shall be paid
by the person in default,and may be deducted from any
compensation payable to theperson, or the
same or any balance may be levied by distressand sale of the
goods and chattels of such person.39Service of documents(1)AnynoticeorotherdocumentrequiredbythisActtobeservedonanypersonmaybeservedonsuchpersonpersonally or by post.(1A)If
such person is absent from the State the document may beserved on the person’s agent in like
manner.(1B)IfsuchpersonisnotknownorhasnoknownagentintheState, the
document shall be served by the publication of thesame,oratrueabstractthereof,inthegazetteandinsomenewspaper
circulating generally in the locality where the landaffected is situated.(2)A
document may be served on the constructing authority bybeing sent by post to the constructing
authority at its office ortotheofficeofsuchpersonastheconstructingauthorityauthorises by public notice to receive
documents on its behalf.40OffencesAlloffencesagainstthisActortheregulationsmaybeprosecuted in a summary way under
theJustices Act 1886.41Disposal of land(1)Notwithstanding any provision of any other
Act, where landhas been taken either pursuant to an
agreement under part 2,division3orbycompulsoryprocessunderthisActand,within7yearsafterthedateoftaking,theconstructingauthoritynolongerrequirestheland,thentheconstructingCurrent as at 1
July 2013Page 55
Acquisition of Land Act 1967Part 5
General[s 42]authority shall
offer the land for sale to the former owner at apricedeterminedbythevaluer-generalundertheLandValuation Act
2010.(1A)Unless sooner
accepted by the former owner the offer shalllapse at the
expiration of 28 days after it is made.(2)In
this section—MinisterincludesarelevantMinister,otherthantheStateDevelopment
Minister.the former ownerin relation to
land means—(a)where only 1 person had an interest in
the land at thedate of acquisition and that person is still
alive or, in thecase of a corporation, in existence—that
person; or(b)in any other case—such person or
persons (if any) as theMinister,intheMinister’sabsolutediscretion,havingregard to the interest that existed in the
land at the dateofacquisition,considerstobefairlyentitledtothebenefit of this section.(3)Apersoncontractingorotherwisedealingwiththeconstructing authority is not concerned to
inquire whether therequirements of this section have been
complied with, and thetitle of such a person to land
acquired from the constructingauthority is not
affected by any failure to comply with thoserequirements.42Regulation-making power(1)TheGovernorinCouncilmayfromtimetotimemakeregulations not inconsistent with this Act
providing for all orany purposes, whether general or to
meet particular cases, thatmay be necessary
or convenient for the administration of thisAct or for
carrying out the objects and purposes of this Act.(2)Aregulationmaybemadeprescribingapenalty,butnotexceeding in any case 1 penalty unit,
for any contravention ofor failure to comply with that or any
other regulation.(3)A regulation may be made about fees
payable under this Act.Page 56Current as at 1
July 2013
Acquisition of Land Act 1967Part 6
Transitional and other provisions[s 43]43Publication of noticesEvery notice given under this Act takes
effect from the day ofits publication.Part 6Transitional and otherprovisionsDivision 1Provision for Acquisition of LandAmendment Act 199944Validating and transitional provisions for
the Acquisitionof Land Amendment Act 1999(1)This section applies if—(a)for the taking of land, a constructing
authority made anapplication for the taking of the land under
section 9(4)orsection15(3A)beforethecommencementofthissection;
and(b)the application was not accompanied by
a copy of a planof survey mentioned in section 9(4)(b) or
section 15(3B)butwasaccompaniedbyaplansufficienttosubstantially identify the land; and(c)the land was taken.(2)Theconstructingauthorityistakentohavecompliedwithsection 9(4)(b)
or section 15(3B).(3)The taking of the land is and always
was valid whether or notthe action required of the Governor in
Council to consider theapplication under section 9(6) or
section 15 was followed.(4)In this Act a
reference to a gazette resumption notice includes,if
the context permits, a reference to—(a)for
a constructing authority—a proclamation publishedin
the gazette under section 9(6) or 15(6)(a); orCurrent as at 1
July 2013Page 57
Acquisition of Land Act 1967Part 6
Transitional and other provisions[s 45](b)forBrisbaneCityCounciloranapprovedlocalgovernment—anotificationpublishedinthegazetteunder section 10(2) or 15(6)(b).(5)A reference to a section in
subsections (2), (3) and (4) is areference to the
section as it was before the commencement oftheAcquisition of Land Amendment Act
1999.Division 2Provision for
Transport and OtherLegislation Amendment Act 200545Transitional provision for taking of
land by Brisbane CityCouncil and other local
governments(1)This section applies if, before the
commencement, BrisbaneCity Council or another local
government had—(a)under section 7, served a notice of
intention to resumefor land on a person; but(b)a notification of resumption for the
land had not beenpublished in the gazette.(2)After the commencement—(a)BrisbaneCityCouncilortheotherlocalgovernmentmay continue to
take the land as if theTransportandOther Legislation Amendment Act 2005,
part 2 had notbeen enacted; and(b)thisActappliestothetakingofthelandasiftheTransport and
Other Legislation Amendment Act 2005,part
2 had not been enacted.(3)In this
section—commencementmeans the
commencement of this section.notificationofresumptionmeansanoticepublishedinthegazetteundersection10(2)asinforcebeforethecommencement.Page 58Current as at 1 July 2013
Division 3Acquisition of
Land Act 1967Part 6 Transitional and other
provisions[s 46]Provisions for
Acquisition of Landand Other Legislation AmendmentAct
200946Making claims for compensationSection 19(3) to (6) does not apply in
relation to a claim forcompensationforlandtakenbyaconstructingauthoritybefore the commencement of this
section.47Recovery of advance against
compensationSection26Adoesnotapplyinrelationtolandtakenbyaconstructingauthoritybeforethecommencementofthissectionif,beforethecommencement,aproceedingfortherecovery of an amount of an advance
made under section 23for the land has started.Division 4Provisions for
Land, Water andOther Legislation Amendment Act201348Definitions for
div 4In this division—commencementmeans the
commencement of the provision inwhich the word
appears.previous, for a
provision of this Act, means the provision as inforce immediately before the
commencement.49Applications under previous section
9(2)(1)This section applies if—(a)beforethecommencement,aconstructingauthorityappliedtotheMinisterforlandtobetakenunderprevious section 9(2); andCurrent as at 1 July 2013Page
59
Acquisition of Land Act 1967Part 6
Transitional and other provisions[s 50](b)onthecommencement,thelandthesubjectoftheapplication had not been taken under
this Act.(2)Section 9, as in force immediately
after the commencement,applies to the application.(3)In this section—Ministersee
previous section 9(1).50Agreements for
taking under previous section 15(1)(1)This
section applies if—(a)before the commencement, a
constructing authority hadenteredanagreementtotakelandunderprevioussection 15(1); and(b)onthecommencement,thelandthesubjectoftheagreement had not been taken under
this Act.(2)Part 2, division 3 applies to the
agreement.51Delegations by Minister(1)This section applies to a delegation
of a Minister made underapreviousdelegationprovisionandineffectimmediatelybefore the
commencement.(2)The delegation has effect from the
commencement as it were adelegation under section 36B.(3)In this section—previous
delegation provisionmeans section 11(5) or 36B asin
force immediately before the commencement.Page 60Current as at 1 July 2013
Schedule 1Acquisition of
Land Act 1967Schedule 1Purposes for
taking landsection 5Part 1Purposes relating totransportation•aviation and related purposes•beacons•bridges•docks•dockyards•ferries•harbours and harbour works•jetties•landing places•lighthouses•locks•parking of vehicles•railways and related purposes•roads•tramways•weighbridges•wharvesCurrent as at 1
July 2013Page 61
Acquisition of Land Act 1967Schedule 1Part 2Purposes relating to theenvironment•protectedareaswithinthemeaningoftheNatureConservation Act
1992, part 4,division 2•soil
conservation•conservation of koalas on land in a
‘Rural Living Area’or‘RegionalLandscapeandRuralProtectionArea’undertheregionalplanfortheSEQregionundertheSustainable Planning Act 2009, if
the land is in the localgovernmentareaoftheBrisbaneCityCouncil,GoldCoast City
Council, Ipswich City Council, Logan CityCouncil, Moreton
Bay Regional Council, Redland CityCouncil or
Sunshine Coast Regional Council•worksfortheprotectionoftheseashoreandlandadjoining the
seashorePart 3Purposes
relating toeducational and culturalfacilitiesPage 62•colleges•kindergartens•libraries•museums•State educational institutions or other
schools•TAFEinstitutesundertheVocationalEducation,TrainingandEmploymentAct2000orTAFEQueensland under
theTAFE Queensland Act 2013•universities or other higher education
institutions•other educational
establishmentsCurrent as at 1 July 2013
Part
4Acquisition of Land Act 1967Schedule 1Purposes
relating to healthservices•ambulance services•healthfacilities,includinghealthcentres,communityhealth centres
and health clinics•hospitalsandservicesrelatedtotheoperationofhospitals•communityresidentialfacilities,includingboardinghouses,refuges,agedcarefacilitiesandfacilitiesforpeople with a disability, social
disadvantage or mentalillnessPart 5Purposes relating to naturalresources•gravel and sand pits•quarriesPart 6Purposes relating to recreation•botanical or other gardens•gymnasiums•markets•parks•public meetings•public music•racecoursesCurrent as at 1
July 2013Page 63
Acquisition of Land Act 1967Schedule 1•recreation grounds•showgrounds•swimming poolsPart 7Purposes relating to water•aqueducts•bore
drains•bores•canals•dams,weirsorotherworksfortheconservationorreticulation of water•drainage•flood gates or flood warnings•flood prevention or flood
mitigation•fords•pumps•quays•reservoirs•wellsPart 8Purposes relating to primaryproductionPage 64•experimental farms•forestry (including afforestation,
silviculture, protectionof forests and forest products,
harvesting, transporting,Current as at 1 July 2013
Acquisition of Land Act 1967Schedule 1milling,
preparing, treating or marketing forest products,access to or for the purposes of forests,
acquisition offorests and forest products and related
purposes)Part 9Purposes
relating to lawenforcement•correctiveservicefacilitiesundertheCorrectiveServices Act
2006•detentioncentresandotherplacesforthepurposesoftheYouth Justice
Act 1992•police•watchhousesPart 10Purposes relating to urbanplanning•civic centres or squares•settingapart,subdividing,resubdividing,reclaiming,alienating,takingup,occupyingorleasinganyunallocated State land, or dealing with
unallocated Stateland in any way in which it may be dealt
with under theLand Act 1994(whether in
carrying out the purposes forwhich the land
is taken, the land is dealt with separatelyor in
conjunction with any adjacent or other unallocatedState land)Current as at 1
July 2013Page 65
Acquisition of Land Act 1967Schedule 1Part 11Purposes relating to sanitation•septic tanks•sewage farms and disposal works and
depots•sewerage•sewers•wastemanagementfacilities,includingrefusetipsandrefuse transfer stationsPart
12Purposes relating to works,construction and facilities•buildings•caravan parks•cemeteries or crematories•departmental and official
purposes•electrical works•fire
stations•pounds•works for the conservation of hydraulic or
other power•works for any public works, or other
work or purpose ofa similar nature•works for the construction or erection of
any public orother works that the constructing authority
is authorisedunder any Act or resolution of Parliament to
construct orerect, or for the purposes of any ActPage
66Current as at 1 July 2013
Part
13Acquisition of Land Act 1967Schedule 1Purposes
relating to non-profitor not-for-profit organisations•non-profitornot-for-profitorganisations,includingacharity,charitableinstitution,publicbenevolentinstitution,
charitable fund and income tax exempt fundPart 14Other purposes•any
purpose declared under a regulation to be a purposefor
which land may be taken under this ActCurrent as at 1
July 2013Page 67
Acquisition of Land Act 1967Schedule 2Schedule 2Dictionarysection 2affectedperson,forlandthesubjectofaresumptionagreement, see
section 15(2).cadastral surveyormeans a person
registered as a cadastralsurveyor under theSurveyors Act
2003.chief executivemeans the chief
executive of the department.chiefexecutive(surveys)meansthechiefexecutiveofthedepartment in
which theSurveyors Act 2003is
administered.constructing authoritymeans—(a)the State; or(b)a
local government; or(c)apersonauthorisedbyanActtotakelandforanypurpose.gazette resumption noticemeans a gazette notice mentionedin
section 9(6) or (7), 15C(5) or 15D(1).gazetting
authority, for a gazette resumption notice,
means—(a)ifthegazetteresumptionnoticewasmadebytheGovernorinCouncil—therelevantMinistertowhomthe application
was made under section 9(1) or 15C(1)fortheland,thesubjectofthegazetteresumptionnotice, to be
taken; or(b)if the gazette resumption notice was
made by a relevantMinister under section 9(7)—the relevant
Minister; or(c)ifthegazetteresumptionnoticewasmadebyaconstructingauthorityundersection15D(1)—theconstructing
authority.landmeans land, or
any estate or interest in land, that is heldin fee simple,
including fee simple in trust under theLand ActPage
68Current as at 1 July 2013
Acquisition of Land Act 1967Schedule 21994,
but does not include a freeholding lease under that Act.multi-parcel purposesee section
3(1).notice of intention to resumesee
section 7(1).objection period, for a notice
of intention to resume, meansthe
period—(a)starting when the notice is served on
the person to whomit is directed; and(b)ending on the day specified in the notice as
the day bywhichanobjectiontothetakingofthelandmaybemade.relevant
Ministermeans—(a)forlandtobetakenforapurposeoftheStateDevelopment and
Public Works Organisation Act 1971,the
State Development Minister; and(b)forlandtobetakenforapurposeoftheTransportInfrastructure
Act 1994, the Minister administering thatAct;
and(c)iftheGovernorinCouncilhas,bygazettenotice,declaredlandtobetakenforapurposeofanotherAct—the Minister
administering the other Act; and(d)otherwise—the Minister administering this
Act.resumption agreementsee section
15(1).StateDevelopmentMinistermeanstheMinisteradministeringtheStateDevelopmentandPublicWorksOrganisation Act 1971.Current as at 1 July 2013Page
69
Acquisition of Land Act 1967Endnotes3KeyKey to abbreviations in list of
legislation and annotationsKeyAIAamdamdtchdefdivexpgazhdginslapnotfdnumo in comorigpparaprecpresprevExplanation=Acts
Interpretation Act 1954=amended=amendment=chapter=definition=division=expires/expired=gazette=heading=inserted=lapsed=notified=numbered=order in council=omitted=original=page=paragraph=preceding=present=previousKey(prev)procprovptpubdR[X]RArelocrenumrep(retro)rvsschsdivSIASIRSLsubunnumExplanation=previously=proclamation=provision=part=published=Reprint No. [X]=Reprints Act 1992=relocated=renumbered=repealed=retrospectively=revised version=section=schedule=subdivision=Statutory Instruments Act 1992=Statutory Instruments Regulation
2002=subordinate legislation=substituted=unnumbered4Table of reprintsA new reprint of
the legislation is prepared by the Office of the Queensland
ParliamentaryCounsel each time a change to the legislation
takes effect.The notes column for this reprint gives
details of any discretionary editorial powers undertheReprints Act 1992used by the
Office of the Queensland Parliamentary Counsel inpreparing it. Section 5(c) and (d) of the Act
are not mentioned as they contain mandatoryrequirementsthatallamendmentsbeincludedandallnecessaryconsequentialamendments be
incorporated, whether of punctuation, numbering or another kind.
Furtherdetails of the use of any discretionary
editorial power noted in the table can be obtained bycontacting the Office of the Queensland
Parliamentary Counsel by telephone on 32370466 or email
legislation.queries@oqpc.qld.gov.au.From29January2013,allQueenslandreprintsaredatedandauthorisedbytheParliamentary Counsel. The previous
numbering system and distinctions between printedand
electronic reprints is not continued with the relevant details for
historical reprintsincluded in this table.ReprintNo.11A rv1B
rv1C rvAmendments to1992 Act No.
641995 Act No. 581997 Act No.
281997 Act No. 78Effective26
March 199328 November 199513 July
19975 December 1997Reprint
date28 January 199429 July
199612 August 199717 December
1997Current as at 1 July 2013Page
71
Acquisition of Land Act 1967EndnotesReprintNo.2 rv2A rv2B
rv2C rv3 rv3A rv3B
rvAmendments to1997 Act No.
781998 Act No. 481999 Act No.
191999 Act No. 442000 Act No.
12001 Act No. 332000 Act No.
63Effective5 December
199718 December 199830 April
19996 September 19991 July
20007 June 20011 July
2001Reprint date25 May
199811 January 199912 May
19997 October 199924 July
200020 June 200115 July
2001ReprintNo.3C3D44A4B4C4D4E55A5B5C5D5E5FAmendments included2003 Act No.
62003 Act No. 19—2004
Act No. 42003 Act No. 702004 Act No.
532005 Act No. 672006 Act No.
29—2007 Act No. 192009 Act No.
52009 Act No. 512009 Act No.
342010 Act No. 392012 Act No.
20Effective4 March
20039 May 20039 May 20036 May
20041 August 200429 November
200427 January 200628 August
200628 August 20061 January
200823 February 200919 November
200929 March 201020 September
201029 August 2012Current as
at14 May 20131 July 2013Amendments included2013 Act No.
232013 Act No. 27NotesR3D
withdrawn, see R4R4E withdrawn, see R5Notes5List of legislationAcquisition of Land Act 1967 No. 48date
of assent 22 December 1967commenced 23 March 1968 (proc pubd gaz
23 March 1968 p 1206)amending legislation—Acquisition of Land Act Amendment Act 1969
No. 33date of assent 19 December 1969commenced on date of assentCity
of Brisbane Town Planning Act and Another Act Amendment Act 1977
No. 22pt 3date of assent 21 April 1977commenced 2 December 1978 (proc pubd gaz 2
December 1978 p 1581)Page 72Current as at 1
July 2013
Acquisition of Land Act 1967EndnotesReal Property
Acts and Other Acts Amendment Act 1986 No. 26 s 4 schdate
of assent 8 April 1986commenced on date of assentCorrective Services (Consequential
Amendments) Act 1988 No. 88 s 3 sch 1date of assent 1
December 1988commenced 15 December 1988 (see s 2(2) and o
in c pubd gaz 10 December 1988 p1675)Water
Resources Act 1989 No. 112 s 1.3 sch 1date of assent 31
October 1989commenced 1 February 1990 (proc pubd gaz 25
November 1989 p 2248)Local Government (Planning and
Environment) Act 1990 No. 61 s 8.8 schs 1–2date of assent 18
September 1990commenced 15 April 1991 (proc pubd gaz 6
April 1991 p 2009)Nature Conservation Act 1992 No. 20 ss 1–2,
159 sch 2 (this Act is amended, seeamending
legislation below)date of assent 22 May 1992ss
1–2 commenced on date of assentremaining
provisions commenced 19 December 1994 (1994 SL No. 472)amending legislation—Nature
Conservation Amendment Act 1994 No. 42 s 2 sch (amends 1992
No.20 above)date of assent 14
September 1994commenced on date of assentLands
Legislation Amendment Act 1992 No. 64 ss 1–3 sch 1date
of assent 7 December 1992ss 1–2 commenced on date of
assentremaining provisions commenced 26 March 1993
(1993 SL No. 88)Land Act 1994 No. 81 ss 1–2, 527 sch 5date
of assent 1 December 1994ss 1–2 commenced on date of
assentremaining provisions commenced 1 July 1995
(1995 SL No. 185)Statute Law Revision Act (No. 2) 1995 No. 58
ss 1–2, 4 sch 1date of assent 28 November 1995commenced on date of assentBody
Corporate and Community Management Act 1997 No. 28 ss 1–2, 295 sch
3date of assent 22 May 1997ss
1–2 commenced on date of assentremaining
provisions commenced 13 July 1997 (1997 SL No. 210)Natural Resources and Other Legislation
Amendment Act 1997 No. 78 pts 1–2date of assent 5
December 1997commenced on date of assentCurrent as at 1 July 2013Page
73
Acquisition of Land Act 1967EndnotesValuation of Land
and Other Legislation Amendment Act 1998 No. 48 pt 1, s 17
schdate of assent 27 November 1998ss
1–2 commenced on date of assentremaining
provisions commenced 18 December 1998 (1998 SL No. 364)Statute Law (Miscellaneous Provisions) Act
1999 No. 19 ss 1–3 schdate of assent 30 April 1999commenced on date of assentAcquisition of Land Amendment Act 1999 No.
44date of assent 6 September 1999commenced on date of assentLand
Court Act 2000 No. 1 ss 1–2, 86 sch 1date of assent 8
March 2000ss 1–2 commenced on date of assentremaining provisions commenced 1 July 2000
(2000 SL No. 165)Corrective Services Act 2000 No. 63 ss 1,
2(2), 276 sch 2date of assent 24 November 2000ss
1–2 commenced on date of assentremaining
provisions commenced 1 July 2001 (2001 SL No. 88)Natural Resources Legislation Amendment Act
2001 No. 33 pts 1, 3date of assent 7 June 2001commenced on date of assentBody
Corporate and Community Management and Other Legislation
AmendmentAct 2003 No. 6 s 1, pt 3date of assent 4
March 2003commenced on date of assentStatute Law (Miscellaneous Provisions) Act
2003 No. 19 ss 1, 3 schdate of assent 9 May 2003commenced on date of assentSurveyors Act 2003 No. 70 ss 1–2, 206 sch
2date of assent 22 October 2003ss
1–2 commenced on date of assentremaining
provisions commenced 1 August 2004 (2004 SL No. 127)Natural Resources and Other Legislation
Amendment Act 2004 No. 4 s 1, pt 2, s 57schdate
of assent 6 May 2004commenced on date of assentStatute Law (Miscellaneous Provisions) Act
2004 No. 53date of assent 29 November 2004commenced on date of assentPage
74Current as at 1 July 2013
Acquisition of Land Act 1967EndnotesTransport and
Other Legislation Amendment Act 2005 No. 67 pts 1–2date
of assent 8 December 2005ss 1–2 commenced on date of
assentremaining provisions commenced 27 January
2006 (2006 SL No. 2)Corrective Services Act 2006 No. 29 ss
1, 2(2), 518 sch 3date of assent 1 June 2006ss
1–2 commenced on date of assentremaining
provisions commenced 28 August 2006 (2006 SL No. 213)Land
and Other Legislation Amendment Act 2007 No. 19 pts 1–2date
of assent 23 April 2007ss 1–2 commenced on date of
assentremaining provisions commenced 1 January
2008 (2007 SL No. 318)Acquisition of Land and Other
Legislation Amendment Act 2009 No. 5 pts 1–2date of assent 23
February 2009commenced on date of assentJuvenile Justice and Other Acts Amendment Act
2009 No. 34 ss 1, 2(2), 45(1) sch pt 1amdt 2date
of assent 17 September 2009ss 1–2 commenced on date of
assentremaining provisions commenced 29 March 2010
(2010 SL No. 37)Building and Other Legislation Amendment Act
2009 No. 51 ss 1, 2(3), pt 12date of assent 19
November 2009commenced on date of assent (see s
2(3))Land Valuation Act 2010 No. 39 ss 1, 325 sch
1 pt 2date of assent 20 September 2010commenced on date of assentMines
Legislation (Streamlining) Amendment Act 2012 No. 20 s 1, ch 2 pt
1date of assent 29 August 2012commenced on date of assentLand,
Water and Other Legislation Amendment Act 2013 No. 23 s 1, pt 3, s
352 sch 1pt 1date of assent 14 May 2013commenced on date of assentTAFE
Queensland Act 2013 No. 27 ss 1–2, 70 sch 1 pt 2date
of assent 3 June 2013ss 1–2 commenced on date of
assentremaining provisions commenced 1 July 2013
(2013 SL No. 108)6List of annotationsShort
titles 1amd 1999 No. 44 s 2 schCurrent as at 1 July 2013Page
75
Acquisition of Land Act 1967EndnotesDefinitionsprov hdgsub
1992 No. 64 s 3 sch 1s 2sub 1992 No. 64 s
3 sch 1amd 2013 No. 23 s 23(4)Note—prev s 2
contained definitions for this Act. Definitions are now
locatedin schedule 2 (Dictionary).Meaning ofmulti-parcel
purposes 3prev s 3 om 1992 No. 64 s 3 sch
1pres s 3 ins 2013 No. 23 s 24Relationship with other Actss
4prev s 4 om 1992 No. 64 s 3 sch 1pres
s 4 ins 2013 No. 23 s 24Part 2—Taking of landDivision 1—Generaldiv hdgins
2013 No. 23 s 352 sch 1 pt 1Purposes for
which land may be takens 5amd 1994 No. 81 s
527 sch 5; 1998 No. 48 s 17 sch; 1999 No. 44 s 2 sch; 2009No. 5
s 3; 2012 No. 20 s 4; 2013 No. 23 s 352 sch 1 pt 1Easementss 6amd
1992 No. 64 s 3 sch 1; 1998 No. 48 s 17 sch; 1999 No. 44 s 2 sch;
2009No. 5 s 4Division 2—Taking
other than by agreementdiv hdgins 2013 No. 23 s
352 sch 1 pt 1Notice of intention to take lands
7amd 1992 No. 64 s 3 sch 1; 1998 No. 48 s 17
sch; 1999 No. 44 s 2 sch; 2003No. 19 s 3 sch;
2005 No. 67 s 5; 2009 No. 5 s 5; 2012 No. 20 s 5; 2013 No.23 s
352 sch 1 pt 1Dealing with objectionss 8amd
1977 No. 22 s 28; 1999 No. 44 s 2 sch; 2009 No. 5 s 6Ways
in which land is to be takenprov hdgamd
1998 No. 48 s 17 schsub 2005 No. 67 s 6(1)s 9amd
1969 No. 33 s 2; 1998 No. 48 s 17 sch; 1999 No. 44 s 3; 1999 No. 44
s 2sch; 2003 No. 19 s 3 sch; 2003 No. 70 s 206
sch 2; 2005 No. 67 s 6(2)–(3);2013 No. 23 s
25Means by which land to be taken by Brisbane
City Council or an approved localgovernmentprov hdgamd
1998 No. 48 s 17 schs 10amd 1969 No. 33 s
3; 1998 No. 48 s 17 sch; 1999 No. 44 s 4; 1999 No. 44 s 2sch;
2003 No. 19 s 3 sch; 2003 No. 70 s 206 sch 2om 2005 No. 67 s
7Page 76Current as at 1
July 2013
Acquisition of Land Act 1967EndnotesAmending of
gazette resumption noticeprov hdgsub 1999 No. 44 s
2 schs 11amd 1999 No. 44 s 2 sch; 2004 No. 53 s
2 sch; 2009 No. 5 s 7; 2013 No. 23 s26Effect of gazette resumption noticeprov
hdgamd 1999 No. 44 s 2 schs 12amd
1969 No. 33 s 4; 1986 No. 26 s 4 sch; 1997 No. 28 s 295 sch 3; 1998
No.48 s 17 sch; 1999 No. 44 s 2 sch; 2003 No. 6
s 119; 2005 No. 67 s 8; 2007No. 19 s 5; 2009
No. 5 s 8; 2012 No. 20 s 6; 2013 No. 23 s 27Constructing
authority must lodge new plan of survey for particular lands
12Ains 2003 No. 6 s 120Particular land
may be dedicated as roads 12Bins 2007 No. 19 s
6amd 2009 No. 5 s 9Provision for
taking particular additional landprov hdgsub
2009 No. 5 s 10(1)s 13amd 1969 No. 33 s 5; 2009 No. 5 s
10(2)–(6)Dealing with title to land affected by
resumptions 14amd 1992 No. 64 s 3 sch 1; 1995 No. 58
s 4 sch 1; 2003 No. 6 s 121Division 3—Taking
by agreementdiv hdgins 2013 No. 23 s
28Subdivision 1—Resumption agreementssdiv
hdgins 2013 No. 23 s 28Meaning ofresumption agreements 15sub
1969 No. 33 s 6amd 1998 No. 48 s 17 sch; 1999 No. 44 s 5;
2003 No. 70 s 206 sch 2; 2005No. 67 s 9sub
2013 No. 23 s 28Subdivision 2—Process for takingsdiv
hdgins 2013 No. 23 s 28Application of
sdiv 2s 15Ains 2013 No. 23 s 28Limit
on taking under sdiv 2s 15Bins 2013 No. 23 s
28Taking by Governor in Councils
15Cins 2013 No. 23 s 28Taking by
constructing authoritys 15Dins 2013 No. 23 s
28Subdivision 3—Miscellaneoussdiv
hdgins 2013 No. 23 s 28Current as at 1
July 2013Page 77
Acquisition of Land Act 1967EndnotesWhen taking is
effectives 15Eins 2013 No. 23 s 28Non-application of sections 7 to 9s
15Fins 2013 No. 23 s 28When constructing
authority is taken to have discontinued resumptions
15Gins 2013 No. 23 s 28No limit on other
acquisition of lands 15Hins 2013 No. 23 s 28Discontinuance of resumption before
publication of gazette resumption noticeprov hdgsub
2005 No. 67 s 10(1)s 16amd 1999 No. 44 s 2 sch; 2005 No. 67 s
10(2); 2013 No. 23 s 352 sch 1 pt 1Revocation before
determination of compensations 17amd
1992 No. 64 s 3 sch 1; 1998 No. 48 s 17 sch; 1999 No. 44 s 2 sch;
2005No. 67 s 11; 2009 No. 5 s 11; 2013 No. 23 s
29By whom compensation may be claimeds
18amd 1992 No. 64 s 3 sch 1; 1997 No. 28 s 295
sch 3; 1998 No. 48 s 17 sch;2009 No. 5 s
12Claim for compensations 19amd
1992 No. 64 s 3 sch 1; 2003 No. 19 s 3 sch; 2009 No. 5 s 13Assessment of compensations
20amd 2009 No. 5 s 14; 2012 No. 20 s 7Grant
of easement etc. or transfer of land in satisfaction of
compensationprov hdgamd 2009 No. 5 s
15(1)s 21amd 2009 No. 5 s 15(2)–(4)Crown
grant in satisfaction of compensations 22amd
1994 No. 81 s 527 sch 5; 1999 No. 44 s 2 sch; 2013 No. 23 s 352 sch
1 pt1Advance against compensations
23amd 1998 No. 48 s 17 sch; 2001 No. 33 s
5Reference of claim for compensation to Land
Courts 24amd 1999 No. 44 s 2 schJurisdiction relating to compensations
26amd 2000 No. 1 s 86 sch 1Jurisdiction about recovery of advance
against compensations 26Ains 2009 No. 5 s
16Powers of Supreme Court in respect of
building unitss 31amd 1998 No. 48 s 17 schPage
78Current as at 1 July 2013
Acquisition of Land Act 1967EndnotesPowers of
District Court for community titles schemes 31Ains
1997 No. 28 s 295 sch 3amd 1999 No. 19 s 3 schMortgagess 32amd
1998 No. 48 s 17 schTaxes, rates and chargess
35amd 1998 No. 48 s 17 schPowers of entry
etc.s 36amd 1995 No. 58 s 4 sch 1; 2003 No. 19
s 3 sch; 2003 No. 19 s 3 schMinister may act
for Crown as constructing authoritys 36Ains
1969 No. 33 s 7Delegation by Ministers 36Bins
1969 No. 33 s 7amd 1999 No. 44 s 2 schsub 2013 No. 23 s
30Temporary occupation of lands
37amd 2003 No. 19 s 3 schDisposal of
lands 41amd 1969 No. 33 s 8; 1998 No. 48 s 17
sch; 2010 No. 39 s 325 sch 1 pt 2;2013 No. 23 s 352
sch 1 pt 1Regulation-making powerprov hdgsub
2004 No. 4 s 57 schs 42amd 1995 No. 58 s 4 sch 1; 1997 No. 78
s 4Publication of noticess 43sub
1999 No. 44 s 2 schPART 6—TRANSITIONAL AND OTHER
PROVISIONSpt hdgins 1999 No. 44 s
6sub 2005 No. 67 s 12Division
1—Provision for Acquisition of Land Amendment Act 1999div
hdgins 2005 No. 67 s 12Validating and
transitional provisions for the Acquisition of Land Amendment
Act1999s 44ins
1999 No. 44 s 6Division 2—Provision for Transport and Other
Legislation Amendment Act 2005div 2 (s
45)ins 2005 No. 67 s 13Division
3—Provisions for Acquisition of Land and Other Legislation
AmendmentAct 2009div 3 (ss
46–47)ins 2009 No. 5 s 17Division
4—Provisions for Land, Water and Other Legislation Amendment Act
2013div 4 (ss 48–51)ins 2013 No. 23 s
31Current as at 1 July 2013Page
79
Acquisition of Land Act 1967EndnotesSCHEDULE
1—PURPOSES FOR TAKING LANDprev sch 1 amd 1989 No. 112 s 1.3 sch
1; 1990 No. 61 s 8.8(1) sch 1om R1 (see RA s
40)pres sch 1 (prev sch (orig sch 2)) amd 1988
No. 88 s 3 sch 1; 1992 No. 20 s159 sch 2 (amd
1994 No. 42 s 2 sch); 1999 No. 44 s 2 schrenum 1999 No. 44
s 2 schamd 2000 No. 63 s 276 sch 2; 2006 No. 29 s
518 sch 3sub 2009 No. 5 s 18amd 2009 No. 51 s
82; 2009 No. 34 s 45(1) sch pt 1 amdt 2num 2013 No. 23 s
32amd 2013 No. 27 s 70 sch 1 pt 2SCHEDULE 2—DICTIONARYins 2013 No. 23 s
33Note—definitions for this Act were
originally located in prev s 2.defaffected personins 2013 No. 23 s
23(2)reloc 2013 No. 23 s 23(3)defapproved local governmentins
1999 No. 44 s 2 schom from prev s 2 2005 No. 67 s 4(1)defcadastral surveyorins 2003 No. 70 s
206 sch 2reloc 2013 No. 23 s 23(3)defchief executiveins 1992 No. 64 s
3 sch 1reloc 2013 No. 23 s 23(3)defchief executive (surveys)ins
1992 No. 64 s 3 sch 1sub 2003 No. 70 s 206 sch 2reloc
2013 No. 23 s 23(3)defconstructing authorityins
1992 No. 64 s 3 sch 1amd 1998 No. 48 s 17 sch; 2004 No. 4 s
3reloc 2013 No. 23 s 23(3)defgazette resumption noticeins
1999 No. 44 s 2 schsub 2005 No. 67 s 4; 2013 No. 23 s
23(1)–(2)reloc 2013 No. 23 s 23(3)defgazetting authorityins
2013 No. 23 s 23(2)reloc 2013 No. 23 s 23(3)deflandins 1992 No. 64 s
3 sch 1amd 1994 No. 81 s 526 sch 5; 2007 No. 19 s
4reloc 2013 No. 23 s 23(3)defmulti-parcel purposeins
2013 No. 23 s 23(2)reloc 2013 No. 23 s 23(3)defnotice of intention to resumeins
1999 No. 44 s 2 schreloc 2013 No. 23 s 23(3)defnotification of resumptionins
1999 No. 44 s 2 schom from prev s 2 2005 No. 67 s 4(1)defobjection periodins 2013 No. 23 s
23(2)reloc 2013 No. 23 s 23(3)defrelevant Ministerins 2013 No. 23 s
23(2)reloc 2013 No. 23 s 23(3)defresumption agreementins
2013 No. 23 s 23(2)reloc 2013 No. 23 s 23(3)Page
80Current as at 1 July 2013